CRY+VIS Interface Meeting
Date: 2021/7/9 13:00-14:00
Participants: Takahashi, Ikeda, Sato, Ushiba, Kimura, Aso, Tomaru, Node, Hirata
Schedule
- IX: To the finalization.
- EX: Alignment for the green beam was finished. To the finalization
- IY: Height adjustment is on going.
- EY: Mirror cleaning is on going in Mitaka. Measurement system had a problem. The shipping will be in the end of next week at earliest.
Status
- Corrugate tube fixing jig: Implementation is scheduled on 7/12-13.
- TM height setting: ITMY.
- Commissioning in air: X-arm.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check: Every Friday.
- PF actuator: After SC.
- Separation of rack in 2F: This is scheduled on 7/16.
- New vacuum pumps for V-chambers: Considering the port location.
- Extension of cables for picomotor drivers: Tested in EYV.
Discussion
Adjustable height range of the filter chain in IY
- The condition of F1 stepper motor is the same as the F3 in IX. We tried to move the motor with the stand alone driver, but the FR is still not working.
- The motor is still not working?
- The FR slider is stuck?
- The range of BF is too small. Check the mechanical stopper.
- Tune the F0 more to lower frequency (now 0.4Hz) in order to extend the range.
Next meeting
- 2021/7/16(FRI)
Klog
EX
17376 ETMX IM dewhitening filters and comb60 filters are implemented , takafumi.ushiba
17396 Oplev preparation at EXC , takaaki.yokozawa
17450 Oplev calibration EX TM oplev , takaaki.yokozawa
17267 Oplev preparation work EX , takaaki.yokozawa
17362 Comment , takaaki.yokozawa
17358 Injection of OpLev lasers to the cryostat at EXC , takafumi.ushiba
17361 Comment , takaaki.yokozawa
EY
17457 dial gauge installation, Pico motor cable extension test , naohisa.satou
17485 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi
General
17369 Added EPICS channel for VIS temperature adjustment , satoru.ikeda
17368 Implemented some Oplev-related fixes to the VIS model file. , satoru.ikeda
17388 Implementation of sensor to EULER matrix for IM photosensors , takafumi.ushiba
17455 TypeA,B,Bp VIS Guardian changed to SAFE , satoru.ikeda
17079 Organizing DAQ channels for VIS , satoru.ikeda
17460 Comment , satoru.ikeda
IX
17400 Modification of damp_temp filter for MN DAMP filter of ITMX , takafumi.ushiba
17405 IX Pico motor driver was broken and replaced. , koji.nakagaki
17449 Oplev calibration IX TM oplevs , takaaki.yokozawa
17468 MNH1 actuator of ITMX seems to have an issue. , takafumi.ushiba
17482 Re-calibration of the IX TM length oplev , takaaki.yokozawa
17481 ITMX MNH1 cable repairement , takafumi.ushiba
17335 Checked resistance of TF and BF LVDT actuators coil. , naohisa.satou
17405 IX Pico motor driver was broken and replaced. , koji.nakagaki
17420 Comment , satoru.ikeda
17449 Oplev calibration IX TM oplevs , takaaki.yokozawa
17468 MNH1 actuator of ITMX seems to have an issue. , takafumi.ushiba
17472 Comment , takafumi.ushiba
8564 ITMX healthy check after pump down , lucia.trozzo
17366 Comment , kouseki.miyo
IY
17406 Setup of pre-isolator , ryutaro.takahashi
17484 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi
17406 Setup of pre-isolator , ryutaro.takahashi
PR2
17478 Rotate PR2 mirror by IM_YAW picomotor but we had better to use traverser , kouseki.miyo
SR2
17434 Cable connection check , naoatsu.hirata
SR3
17439 Cable connection check , naoatsu.hirata
SRM
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
Type-A
- Adjusted the ballasts on the cryo-payload and the BF in IY. Additional spring was implemented on the BF.
- Repaired the broken cables for TF/BF actuator opening the chamber. The BF and TF were recovered and the chamber was closed.
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Adjustment of IYV
- Type-B team: MSB
Milestone
IMC suspensions are ready in air [40] will finish 2021/04/21.
PRs are ready in air [643] will finish 2021/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2021/11/24.
SRs are ready in air [663] will finish 2021/12/20.
Output suspensions are ready in air [695] will finish 2021/12/21.
TMSY is ready in air [708] will finish 2021/??/??.
TMSX is ready in air [684] will finish 2021/??/??.
2021/03/29 updated
Safety
Discussion
Travel Plans
The week from 7/5
- Takahashi: 7/5-8 (KIW8 7/7-9)
- Sato: 7/5-8
- Hirata: 7/5-9
- Yano: 7/5-9
The week from 7/12
- Takahashi: 7/12-16
- Sato: 7/12-16
- Hirata: 7/12-16
- Yano: 7/12-16
Next meeting
- 2021/7/16(FRI)