 * Adjusted the height of GAS filters and measured the height of TMs in IY and EY.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2021/9/3 13:00-

Participants:

Post O3 Upgrade portal

Schedule

  • IX: In finalization. Health check.
  • EX: In finalization. Health check. Installation of ACCs should be scheduled.
  • IY: TM height was adjusted/measured on 9/1.
  • EY: Weight and Yaw were adjusted on 9/2. Chamber closing is scheduled on 9/6-8.

Status

  • TM height setting: Height of ITMY/ETMY was measured.
  • Commissioning in air: Health check. Oplev setting.
  • Commissioning in vacuum:
  • Overall commissioning:
  • Acceptance check: Every Friday.
  • PF actuator: At the in-vacuum commissioning.
  • New vacuum pumps for V-chambers:
  • Heater control:

Discussion


VIS Meeting

Date: 2021/9/3 14:00-

Participants:

Summary Report

Type-A

  • Adjusted the height of GAS filters and measured the height of TMs in IY and EY.

Type-B

Type-Bp

Type-C

Electronics

Control

Schedule

See Schedule

  • Type-A team:
  • Type-B team:

Milestone

  • IMC suspensions are ready in air [40] will finish 2021/04/21.

  • PRs are ready in air [643] will finish 2021/07/09.

  • ETMX is ready in air [656] will finish 2021/08/25.

  • ITMX is ready in air [657] will finish 2021/08/31.

  • ETMY is ready in air [658] will finish 2021/09/16.

  • ITMY is ready in air [659] will finish 2021/11/08.

  • BS is ready in air [691] will finish 2021/11/24.

  • SRs are ready in air [663] will finish 2021/12/20.

  • Output suspensions are ready in air [695] will finish 2021/12/21.

  • TMSY is ready in air [708] will finish 2021/??/??.

  • TMSX is ready in air [684] will finish 2021/??/??.

2021/03/29 updated

Safety

Discussion

Travel Plans

The week from 9/6

  • Takahashi: 9/6-10
  • Sato: 9/6-10
  • Hirata: 9/6-9
  • Yano: 9/6-10

The week from 9/13

Next meeting

  • 2021/9/10(FRI)

KAGRA/Subgroups/VIS/VISMinutes20210903 (last edited 2021-09-03 14:24:03 by RyutaroTakahashi)