CRY+VIS Interface Meeting
Date: 2021/10/1 13:00-
Participants:
Schedule
- IX: Health check. Effect due to the convection was investigated. LVDT driver for the IP was replaced.
- EX: Health check. Installation of ACCs will be scheduled after the health check.
- IY: H4 geophone was assembled. Yaw picomotor in BF is not working.
- EY: Cables for the BF damper were repaired.
Status
- TM height setting: ITMY is too low.
- Commissioning in air: Health check.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers:
- Heater control:
Discussion
VIS Meeting
Date: 2021/10/1 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Health check in IX and EX.
- Type-B team:
Milestone
IMC suspensions are ready in air [40] will finish 2021/04/21.
PRs are ready in air [643] will finish 2021/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2021/11/24.
SRs are ready in air [663] will finish 2021/12/20.
Output suspensions are ready in air [695] will finish 2021/12/21.
TMSY is ready in air [708] will finish 2021/??/??.
TMSX is ready in air [684] will finish 2021/??/??.
2021/03/29 updated
Safety
- T3 Red in Y-arm had an accident.
Discussion
Travel Plans
The week from 10/4
- Takahasdhi: 10/4-8
- Sato: 10/4-8
- Hirata: 10/4-8
- Yano: 10/4-8
The week from 10/11
- Takahashi: 10/11-15
- Sato: 10/11-15
- Hirata: 10/11-15
- Yano: 10/11-15
Next meeting
- 2021/10/8(FRI)