Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/3/18 13:00-
Participants:
Schedule
- IX: Adjustment after the earth quake.
- EX: Adjustment after the earth quake.
- IY: Health check.
- EY: IP tuning, Health check. Go to recovery of F2.
Status
- Replacement of flip cables: TMS.
- TM height setting: ITMY.
- Oplev: IY.
- ACC: Installation was finished.
- Commissioning in air: Alignment of ITMY.
- Commissioning in vacuum:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers: Ion pumps delivery.
- Heater control: Test in IXV/EXV.
- TMS:
Discussion
VIS Meeting
Date: 2022/3/18 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Recovery of F2 in EY.
- Type-B team:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 3/21
- Takahashi: 3/22-24
- Sato: 3/22-24
- Hirata: 3/23-25
The week from 3/28
- Takahashi: 3/29-4/1
- Sato: 3/29-4/1
- Hirata: 3/29-4/1
Next meeting
- 2022/3/25(FRI)