Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/5/6 13:00-14:00

Participants: Takahashi, Node, Kimura, Uchiyama, Aso, Akutsu, Ushiba

Post O3 Upgrade portal

Schedule

  • IX: F3 GAS glitch.
  • EX:
  • IY: Finalization. Height adjustment. Health check. Cabling check. H2 geophone noise. Thermometer.
  • EY: Finalization. Health check. IM V3 cabling. BF LVDT noise. Cabling check (P7-2 upperside). ADC noise on MN/IM PS.
  • Type-B: Health check in SR3. Calibration of geophone in SR2. Stand-alone SM driver for SR3.
  • Type-Bp: Traverser limit SW. FC onto PRM.
  • Type-C: OMC installation from 5/23.

Status

  • Replacement of flip cables: Cables for TMS.
  • TM height setting: ITMY.
  • Oplev: Windshield in the next.
  • ACC:
  • Commissioning in air:
  • Commissioning in vacuum:
  • Acceptance check: Review from 5/23.
  • PF actuator: At the in-vacuum commissioning.
  • New vacuum pumps for V-chambers: How to treat thermal load.
  • Heater control: Pending.
  • TMS: Thermometet
  • Cryo-shield: Finnese measurement, height check --> Cooler ON.

Discussion


VIS Meeting

Date: 2022/5/6 14:00-14:10

Participants: Takahashi, Washimi, Uchiyama, Aso, Ushiba

Summary Report

Type-A

  • Height adjustment of ITMY/ETMY.

Type-B

  • TF measurement in SR3.

Type-Bp

  • Preparation for the traverser limit switches.

Type-C

Electronics

Control

Schedule

See Schedule

  • Type-A: Finalization in IY/EY.
  • Type-B/Bp/C: FC onto PRM, Alignment of SR3/OMMC.

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 5/9

  • Takahashi: 5/9-13
  • Sato: 5/9-13
  • Hirata: 5/9-13

The week from 5/16

  • Takahashi: 5/17-20
  • Sato: 5/17-20
  • Hirata: 5/17-20

Next meeting

  • 2022/5/13(FRI)