Size: 1784
Comment:
|
Size: 1998
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 32: | Line 32: |
* New vacuum pumps for V-chambers: | * New vacuum pumps for V-chambers: When should we implement the ion pumps? It is better to do before cooling. |
Line 34: | Line 34: |
* TMS: Window to EYT. | * TMS: DN400 flange for the window in EYT. |
Line 45: | Line 45: |
* Monitored during the pump down in EY. |
|
Line 47: | Line 49: |
* Investigated the suspension in PR2. * Cable check in PR2/PR3/PRM. |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/7/1 13:15-13:40
Participants: Takahashi, Hirata, Ikeda, Miyoki, Yokozawa, Ushiba, Akutsu, Kimura, Aso
Schedule
- IX:
- EX:
- IY: To cooling.
- EY: Repair of the leak point. Health check and pump-down. Leak test in the next week.
Type-B: Recovery of the alignment after cleaning in SR3. Characterization of the OpLev in SR2. Installation of the MSBs in SR3 and SRM. Replacement of the mirror in SRM in the next week.
- Type-Bp: Investigation of the PR2 suspension. Calibration of the BF damper LVDT in PRM. Cable check in PR2, PR3, and PRM.
- Type-C: Health check should be scheduled.
Status
- Replacement of flip cables: EXT and BF temp.
- TM height setting:
- Oplev: Wind shield for Type-Bp.
- ACC:
- Commissioning in air:
- Commissioning in vacuum:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers: When should we implement the ion pumps? It is better to do before cooling.
- Heater control: Pending.
- TMS: DN400 flange for the window in EYT.
Discussion
VIS Meeting
Date: 2022/6/24 14:00-
Participants:
Summary Report
Type-A
- Monitored during the pump down in EY.
Type-B
Type-Bp
- Investigated the suspension in PR2.
- Cable check in PR2/PR3/PRM.
Type-C
Electronics
Control
Schedule
- Type-A:
- Type-B: Mirror replacement in SRM.
- Type-Bp:
- Type-C:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 7/4
- Takahashi: 7/5-8
- Sato:
- Hirata: 7/5-8
The week from 7/11
- Takahashi:
- Sato:
- Hirata:
Next meeting
- 2022/7/8(FRI)