Date: 2022/7/15 13:00-
Participants:
Schedule
- IX: Offload of GAS filters.
- EX:
- IY: Health check and recovery.
- EY: Health check and recovery. Installation of the MNV oplev.
- Type-B: Health check.
- Type-Bp: Investigation of the previous data on PR2.
- Type-C: Health check of the IMMT1/2.
Status
- Replacement of cables: EXT and BF temp.
- TM height setting:
- Oplev:
- ACC:
- Commissioning in air:
- Commissioning in vacuum: Keeping the X-arm. Health check in Y-arm.
- Acceptance check: Type-Bp.
- New vacuum pumps: Schedule on the installation of the ion pumps.
- Heater control: Pending.
- TMS:
Discussion
VIS Meeting
Date: 2022/7/15 14:00-
Participants:
Summary Report
Type-A
- Health check. Recovered the F2 in IY and the F1 in EY.
- Offloaded the GAS filters in IX.
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
- Type-A:
- Type-B: Health check.
- Type-Bp:
- Type-C:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 7/19
- Sato: 7/19-22
- Hirata: 7/19-22
The week from 7/25
- Takahashi:
- Sato: 7/26-29
- Hirata: 7/26-29
Next meeting
- 2022/7/22(FRI)