Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/9/9 13:00-
Participants:
Schedule
- Type-A: Recovery of the BF H2 LVDT.
- Type-B: Closing of the chambers. Tightening of the screws for the chamber legs. Setting of the dial gauges.
- Type-Bp: Closing of the chambers.
- Type-C:
Status
- Replacement of cables: EXT and EX remain.
- TM height setting:
- Oplev:
- ACC:
- Commissioning in air:
- Commissioning in vacuum:
Acceptance check: DropboxPaper
- Vacuum system: Pump down of the center area from 9/12.
- Heater control: Pending.
- TMS:
Discussion
VIS Meeting
Date: 2022/9/9 14:00-
Participants:
Summary Report
Type-A
- Recovered the BF H2 LVDT.
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
- Type-A:
- Type-B: Monitor of the evacuation.
- Type-Bp: Monitor of the evacuation.
- Type-C:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 9/12
- Sato: 9/12-15
- Hirata: 9/12-16
The week from 9/5
- Takahashi: 9/20-22
- Aso: 9/20-22
Next meeting
- 2022/9/16(FRI)