Line 8: Line 8:
Date: 2022/9/16 13:00- Date: 2022/9/16 13:00-13:15
Line 10: Line 10:
Participants: Participants: Takahashi, Yokozawa, Miyoki, Aso, Akutsu, Ushiba, Ikeda, Node
Line 15: Line 15:
 * Type-A: Installation of the windshields in EY.  * Type-A: Installation of the windshields in EY. Improvement of the controls.
Line 18: Line 18:
 * Type-C: Shift of the OMMT2 suspension in the next week.  * Type-C: Health check of the IMMT suspensions. Shift of the OMMT2 suspension in the next week.
Line 23: Line 23:
 * Oplev:  * Oplev: Adjustment of the PR2 oplev.
Line 28: Line 28:
 * Vacuum system: Pump down of the center area from 9/13.  * Vacuum system: Pump down of the center area from 9/13. Large leak in PR3-PRM and SR3-SRM.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/9/16 13:00-13:15

Participants: Takahashi, Yokozawa, Miyoki, Aso, Akutsu, Ushiba, Ikeda, Node

Post O3 Upgrade portal

Schedule

  • Type-A: Installation of the windshields in EY. Improvement of the controls.
  • Type-B: Monitoring of the evacuation.
  • Type-Bp: Recovery of the BF GAS in PR3. Monitoring of the evacuation. Centering of the oplev in PR2.
  • Type-C: Health check of the IMMT suspensions. Shift of the OMMT2 suspension in the next week.

Status

  • Replacement of cables: EXT remains.
  • TM height setting:
  • Oplev: Adjustment of the PR2 oplev.
  • ACC:
  • Commissioning in air:
  • Commissioning in vacuum: MICH and FPMI Lock.
  • Acceptance check: DropboxPaper

  • Vacuum system: Pump down of the center area from 9/13. Large leak in PR3-PRM and SR3-SRM.
  • Heater control: Pending.
  • TMS:

Discussion


VIS Meeting

Date: 2022/9/16 14:00-

Participants:

Summary Report

Type-A

Type-B

Type-Bp

Type-C

Electronics

Control

Schedule

  • Type-A:
  • Type-B:
  • Type-Bp:
  • Type-C: Shift of the OMMT2 suspension. Health check of the IMMT suspensions.

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 9/19

  • Takahashi: 9/20-22
  • Aso: 9/20-22

The week from 9/26

  • Takahashi:
  • Sato:
  • Hirata:

Next meeting

  • 2022/9/30(FRI)

KAGRA/Subgroups/VIS/VISMinutes20220916 (last edited 2022-09-16 17:24:52 by RyutaroTakahashi)