Line 18: Line 18:
 * Technical overview (Matteo)
Line 22: Line 23:
   * etc.     * Available flanges on OMC or OMMT chambers
    * Can we penetrate the X-arm duct ?
    * Cryostat door interference ?
 - Put GVs to make a removable section next to IYC
    * Vacuum modifications in conjunction with overall KAGRA vacuum upgrade ?
Line 26: Line 31:
    * Doubly resonant OPO
    * In-vac OPO ?
Line 27: Line 34:
    * Squeezer -> FC
    * FC -> MIF
   * Back scattering mitigation
    * Theoretical study on requirements
    * New IFI ?
Line 30: Line 42:
    * FC LSC
    * FC ASC
    * ASC for FC->MIF coupling
   * Control system hardware
Line 32: Line 48:
  * Milestones for the preliminary design

KAGRA Filter Cavity Kick-off meeting

Date/Time/Location

2021 Jan. 20th from 10AM

Connection: KAGRA Zoom2

Abstract

This is a project to install a filter cavity into KAGRA. It is not funded yet, but we should start preliminary design studies to prepare for the time when a fund is available. This meeting's purpose is to gather interested people and identify potential tasks to start this project.

Agenda

  • Introduction (Aso)
  • Technical overview (Matteo)
  • Identification of Tasks
    • Clarify the constraints
      • Available space, location
      • Vacuum interface
        • Available flanges on OMC or OMMT chambers
        • Can we penetrate the X-arm duct ?
        • Cryostat door interference ?
          • - Put GVs to make a removable section next to IYC
        • Vacuum modifications in conjunction with overall KAGRA vacuum upgrade ?
    • Preliminary design
      • Filter Cavity Optical Design
      • Squeezer design
        • Doubly resonant OPO
        • In-vac OPO ?
      • Interface optics design
        • Squeezer -> FC

        • FC -> MIF

      • Back scattering mitigation
        • Theoretical study on requirements
        • New IFI ?
      • Suspension design
      • Vacuum design
      • Control system
        • FC LSC
        • FC ASC
        • ASC for FC->MIF coupling

      • Control system hardware
        • Analog electronics
        • DGS
    • Milestones for the preliminary design
    • Make a realistic budget
    • Make a project schedule
  • Confirm available members
  • Schedule regular meetings