Line 32: Line 32:
== Cabling ==
LVDT/Act - (coil wires) - Dsub9M - (Dsub9F - PTFE 2m - Dsub9F) - Dsub9M flange - Flipper cable - Dsub Cable
Geophone - (MIL C 26482 - PTFE 0.5m - Dsub9M) - (Dsub9F - 1.5m PTFE - Dsub9F) - Dsub9M flange - Flipper cable - Dsub Cable

Transmission Monitor's Vibration Isolation Stage: preparation (TMS-VIS)

  • With a fixed stage.
  • TMS = BRT (beam reducing telescope) + GPT (Gouy phase telescope)

<< <  2018 / 5 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      

<< <  2018 / 6 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  

LVDTs

Actuator coils

Geophones

Cabling

LVDT/Act - (coil wires) - Dsub9M - (Dsub9F - PTFE 2m - Dsub9F) - Dsub9M flange - Flipper cable - Dsub Cable Geophone - (MIL C 26482 - PTFE 0.5m - Dsub9M) - (Dsub9F - 1.5m PTFE - Dsub9F) - Dsub9M flange - Flipper cable - Dsub Cable

Task list

Note: some of the tasks can be done in parallel.

Signal Assign

Pin Name

Resistance

Equipment

Assign

Comment1

Comment2

Connection

KAGRA/subgroup/AOS/TMS-VIS0 (last edited 2018-10-24 19:00:52 by TomotadaAkutsu)