* ISC Task List 2015 (Updated after the meeting) http://www.evernote.com/l/AGHCMq59o25EKK0TsfE3RgA6FfhobJlq7QE/ ==== Comments ==== * iKAGRA commissioning: * Need to be prepared befoe starting the commissioning. * We should make a noise budget model beforehand. * Also we should perform necessary measurements (such as PD dark noise) as much as possible beforehand. * IBF: Only considering the power reduction of the RFSB is not enough. We should estimate the actual impacts on the loop noise, ASC, etc. We should check with Hirose-san how much assymmetry between X and Y arms were introduced with his simulations. Also |
Minutes of ISC Meeting on 2015/7/27
14:00 - 15:00 on SeeVogh
Participants: Aso, Miyakawa, Kokeyama, Somiya, Arai, H. Yamamoto, Ueda, Nakano, Akutsu, Michimura
Agenda
- Review the task list again
- Confirmation of available man power
Discussions
Review of the task list again
- ISC Task List 2015 (Updated after the meeting)
http://www.evernote.com/l/AGHCMq59o25EKK0TsfE3RgA6FfhobJlq7QE/
Comments
- iKAGRA commissioning:
- Need to be prepared befoe starting the commissioning.
- We should make a noise budget model beforehand.
- Also we should perform necessary measurements (such as PD dark noise) as much as possible beforehand.
- IBF: Only considering the power reduction of the RFSB is not enough. We should estimate the actual impacts on the loop noise, ASC, etc. We should check with Hirose-san how much assymmetry between X and Y arms were introduced with his simulations. Also