ISC Meeting on 2015/8/10
2015/8/10 14:00 - 15:00
Participants: Miyakawa, Kokeyama, Aso, Michimura, Hirose, Hiro Yamamoto, Ueda, Arai, Somiya, Uehara, Nakano
Discussions
Task assignment
- Some task assignments were confirmed.
- Aso will ask absent people about their task assignments.
- Need to specify the task definitions more in detail.
Output optics overall design
- Need to fix the vacuum chamber layout by the F2F in August so that we can order the clean booth.
- Should be able to fix the positions once the Gouy phase change of the OMC is fixed (this will in turn determine the OMMT design)
We also need to decide on the height of the chambers -> depends on the type of vibration isolation system to be used.
A/I: Somiya-san will send us the current status. We will discuss this at the next ISC meeting.
bKAGRA roadmap
- Please give me (Aso) your opinions.
Next Meeting
8/24 14:00 - 15:00
Agenda
- Output Optics Layout