ISC Meeting on 2015/8/10

2015/8/10 14:00 - 15:00

SeeVogh

Participants: Miyakawa, Kokeyama, Aso, Michimura, Hirose, Hiro Yamamoto, Ueda, Arai, Somiya, Uehara, Nakano

Discussions

Task assignment

  • Assignment plan with comments

  • Some task assignments were confirmed.
  • Aso will ask absent people about their task assignments.
  • Need to specify the task definitions more in detail.

Output optics overall design

  • Need to fix the vacuum chamber layout by the F2F in August so that we can order the clean booth.
  • Should be able to fix the positions once the Gouy phase change of the OMC is fixed (this will in turn determine the OMMT design)
  • We also need to decide on the height of the chambers -> depends on the type of vibration isolation system to be used.

  • A/I: Somiya-san will send us the current status. We will discuss this at the next ISC meeting.

bKAGRA roadmap

  • Slides

  • Please give me (Aso) your opinions.

Next Meeting

8/24 14:00 - 15:00

Agenda

  • Output Optics Layout