ISC Meeting on 2015/12/14
14:00 - 15:00 on SeeVogh
Participants: Arai, Miyakawa, Kokeyama, Aso, Hirose, Michimura
- Requests for coating requirements from LMA (Aso)
- SRM HR transmission: relax the tolerance to T=0.15+/-0.01
- Inspiral Range:
- T=14% 155.467Mpc
- T=15.36% 153.901Mpc
- T=16% 153.163Mpc
- Not a big difference: the relaxed tolerance is acceptable.
- Hirose already told LMA that the relaxed requirements are acceptable.
- Need to update the Wiki
- Electronics Preparation Status (Michimura, Aso)
- Cable (Michimura)
- We have all the necessary cables
- RF distribution (Komori, Michimura)
The panel should have been delivered to Kamioka -> Found it.
Need to arrange people to assemble the box -> Nakano-kun did it.
- RFPD/QPD (Aso, Doi)
There are some problems with the mis-match between the regulator height and the screw holes on the box. -> Will fix the regulator with a plate. Use insulating plates.
- Site installation work schedule
- We will make a task list. Then assign tasks to people and arrange the schedule.
- Michimura will make a task list.
- When to install the LSC rack ? Need to coordinate with the duct installation schedule.
- Cable (Michimura)
- Magnet Noise (Michimura)
What was the reason for chosing 2mm dia, 3mm long SmCo ?
- Michimura will summarize the noise estimates with the above magnet size
- OMC (Somiya)
- No update
- FFT Simulation (Hirose, H. Yamamoto)
- No update
- Next meting 2016/1/12