ISC Meeting on 2016/1/12
14:00 - 15:00 on SeeVogh
Participants: Michimura, H. Yamamoto, K. Arai, Aso, Akutsu
- Electronics Preparation Status (Michimura, Aso)
- RFPD/QPD (Aso, Doi): Waiting for delivery
- RF Distribution Amp assembled by Nakano on Dec 16, 2015
- All the iKAGRA ISC chassis (minimum set) are assembled
- iKAGRA electronics tasklist
- RF PD
- assembly (Aso, Doi)
- test, tune resonances (?)
- Cable assembly
- RF low loss cables with N connectors
- For short (less than 10m) cables, will not use the semi-rigid low-loss cables. Ask a company to make a bunch of flexible coaxial cables with N connectors (and some long SMA cables).
- Diff-to-single cables: Only 2 of them are needed. Make them as a part of installation work.
- we have purchased all the other ISC cables
- RF low loss cables with N connectors
- Cabling
- IMC ASC related (Nakano, U-Toyama students?)
- REFL related (Michimura, Ando-lab students)
- IMMT1T(RFPD,DCQPDx2) related (Michimura, Ando-lab students)
- We have decided not to use IMMT2T in the IOO meeting
- Magnet noise
SmCo 2mm dia, 3mm thick for BS TM is OK
- magnetic noise from TM: ~1/18 of the displacement noise requirement at 10 Hz
- DAC output at lock acquisition for TM: ~630 counts
SmCo 10mm dia, 10mm thick for BS IM (no change in size)
- Magnetic noise from IM: ~1/20 of the displacement noise requirement at 10Hz
- DAC output during lock for IM: ~3425 counts RMS
- See JGW-T1504450 for the summary of the discussion (includes the discussion for SRs and PRs)
- FFT simulation (H. Yamamoto, Hirose)
- Need transmission data of ETM. What is the status of delivery ?
- H. Yamamoto will prepare the simulation code so that once the data is available, we can quickly check the requirements on the ITM polishing.
- Initial Alignment of iKAGRA.
- How to send the beam to the end at 3km away ?
- Automatically scan the beam direction using PR3 (for X arm) and check for flashes on the ETM suspension using a video camera.
- Automation of the above process is an interesting project for students
- How to send the beam to the end at 3km away ?
- Next meting 2016/1/25