Size: 2018
Comment:
|
← Revision 34 as of 2018-12-05 12:28:40 ⇥
Size: 4853
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
[[LCGT/Meeting/f2f/2018Dec|Main F2F Page]] |
|
Line 3: | Line 5: |
Dec. 4th (Tue) 13:30 - 17:00 | Dec. 4th (Tue) 13:30 - 17:30 |
Line 7: | Line 9: |
Zoom connection: https://zoom.us/j/5045179604 |
|
Line 8: | Line 12: |
||<rowbgcolor="#E0FFFF"12% style="text-align:center">Time ||<style="text-align:center">Subject and Title ||<24% style="text-align:center">Speaker ||File || ||13:30-13:45 ||Explanation of the context ||Y. Aso ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || ||<rowbgcolor="#FFFFE0" rowstyle="text-align:left; ">13:45-14:45 ||||<style="text-align:left;">'''Report of past activities''' || || || ||Past studies/discussions of Advanced R&D subsystem ||Y. Michimura ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || ||<rowbgcolor="#E0E0FF" rowstyle="text-align:left; ">14:45-15:00||||<style="text-align:left;">Break|| || ||<rowbgcolor="#FFFFE0" rowstyle="text-align:left; ">15:00-16:30 ||||<style="text-align:left;">'''Contributed talks''' || || || || || ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || || || || ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || || || || ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || || || || ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || || || || ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || || || || ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || ||<rowbgcolor="#FFFFE0">12:30-13:45 ||||<style="text-align:center">Lunch || || ||<rowbgcolor="#FFFFFF" rowstyle="text-align:left; ">12:35-12:55 ||||<style="text-align:left;">''' Safety Lecture''' || || || ||Safety Lecture in English (20 min) ||Takashi Uchiyama (ICRR) ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|x]] || |
||<rowbgcolor="#E0FFFF"16% style="text-align:center">Time ||<style="text-align:center">Subject and Title ||<24% style="text-align:center">Speaker ||File || ||13:30-13:45 ||Explanation of the context ||Y. Aso ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9376|O]] || ||<rowbgcolor="#FFFFE0" rowstyle="text-align:left; ">13:45-14:45 ||||<style="text-align:left;">'''Report of past activities in Advanced R&D group''' || || || ||Summary of Past Discussions on KAGRA Upgrade ||Y. Michimura ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9313|(>_<)]] || ||<rowbgcolor="#E0E0FF" rowstyle="text-align:left; ">14:45-15:00 ||||<style="text-align:left;">'''Break''' || || ||<rowbgcolor="#FFFFE0" rowstyle="text-align:left; ">15:00-16:15 ||||<style="text-align:left;">'''Contributed talks''' || || ||10 min ||R&D of 100kg sapphire crystals ||E. Hirose ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9363|o]] || ||10 min ||R&D of frequency dependent squeezer ||Ray-Kuang Lee/NTHU ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9357|o]] || ||10 min ||R&D of Newtonian noise measurement ||Tomofumi Shimoda (U-Tokyo) ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9368|o]] || ||20 min ||TAMA300 filter cavity exp. status ||Yu-hang Zhao and Chien-Ming Wu ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9377|o]] || ||10min ||EPR entanglement ||K. Somiya ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9365|o]] || ||10min ||Engineering management for KAGRA upgrade ||Y. Aso ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9361|O]] || ||<rowbgcolor="#E0E0FF" rowstyle="text-align:left; ">16:15-16:30 ||'''Break''' || ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=XXXX|x]] || ||<rowbgcolor="#FFFFE0" rowstyle="text-align:left; ">16:30-17:30 ||||<style="text-align:left;">'''Discussion''' || || || || || || || ---- == Minutes == === Introduction by Aso === * Why FPC is proposed ? * Purpose/Scope of FPC * Steps to start FPC === Summary of the past upgrade studies by Michimura === * Extensive studies have already been carried out * Several options were compared * High frequency optimized plan seems better * Candidates for short term upgrade (cheap, quick) and longer term upgrade (larger change and more expensive) were discussed === Contributed talks by various people === * 100kg sapphire (Hirose) * Frequency dependent squeezing (Lee) * Newtonian noise measurement (Shimoda) * TAMA300 filter cavity (Zhao, Wu) * EPR entanglement (Somiya) * Engineering management (Aso) === Discussion === ==== What should be included in the white paper ==== * Scientific motivation * Survey of the current technologies * Cheap, Expensive * Ready, Not ready * Limits of the current facility * Trade-off studies * Two plans * Near term upgrade plan * Longer term upgrade plan * Back up plans * R&Ds to be done * Budget for R&D * Budget estimate * Project execution plan ==== Schedule for the white paper ==== * Work in progress draft to be presented @ KIW in Feb 2019 * Get feedbacks from Virgo people * First draft to be circulated @ April 2019 F2F * Final version to be put for approval @ Aug 2019 F2F ==== How to proceed the discussion ? ==== * Make a skelton of the white paper first * Dig deeper into each item with sub-groups ==== Other discussion ==== * Definitions of short term and longer term upgrades * Short term: after O4 (~ in 5 years) * Longer term: after O5-6 ? ~ in 10 years * This should be discussed in FPC * How to get funding should be discussed with relevant people (ICRR, senior people in collaborating countries, etc) in parallel with the white paper writing. * Need to keep ICRR in the circle. * Review (external/internal) of the white paper may be necessary before submitting to the KSC and EO for approval. * The white paper should be updated with changing environment * How RDC should select KAGRA project R&Ds before the white paper is finalized ? * RDC may be able to make interim approvals * These interim KAGRA project R&Ds should be checked against the white paper once it is ready * Should be discussed more in the KSC session. |
Satellite Meeting on Future Upgrade of KAGRA
Date/Time/Venue
Dec. 4th (Tue) 13:30 - 17:30
Large seminar room (3201) in Subaru building (the same as the main F2F meeting)
Zoom connection: https://zoom.us/j/5045179604
Program
Time |
Subject and Title |
Speaker |
File |
13:30-13:45 |
Explanation of the context |
Y. Aso |
|
13:45-14:45 |
Report of past activities in Advanced R&D group |
|
|
|
Summary of Past Discussions on KAGRA Upgrade |
Y. Michimura |
|
14:45-15:00 |
Break |
|
|
15:00-16:15 |
Contributed talks |
|
|
10 min |
R&D of 100kg sapphire crystals |
E. Hirose |
|
10 min |
R&D of frequency dependent squeezer |
Ray-Kuang Lee/NTHU |
|
10 min |
R&D of Newtonian noise measurement |
Tomofumi Shimoda (U-Tokyo) |
|
20 min |
TAMA300 filter cavity exp. status |
Yu-hang Zhao and Chien-Ming Wu |
|
10min |
EPR entanglement |
K. Somiya |
|
10min |
Engineering management for KAGRA upgrade |
Y. Aso |
|
16:15-16:30 |
Break |
|
|
16:30-17:30 |
Discussion |
|
|
|
|
|
|
Minutes
Introduction by Aso
- Why FPC is proposed ?
- Purpose/Scope of FPC
- Steps to start FPC
Summary of the past upgrade studies by Michimura
- Extensive studies have already been carried out
- Several options were compared
- High frequency optimized plan seems better
- Candidates for short term upgrade (cheap, quick) and longer term upgrade (larger change and more expensive) were discussed
Contributed talks by various people
- 100kg sapphire (Hirose)
- Frequency dependent squeezing (Lee)
- Newtonian noise measurement (Shimoda)
- TAMA300 filter cavity (Zhao, Wu)
- EPR entanglement (Somiya)
- Engineering management (Aso)
Discussion
What should be included in the white paper
- Scientific motivation
- Survey of the current technologies
- Cheap, Expensive
- Ready, Not ready
- Limits of the current facility
- Trade-off studies
- Two plans
- Near term upgrade plan
- Longer term upgrade plan
- Back up plans
R&Ds to be done
Budget for R&D
- Budget estimate
- Project execution plan
Schedule for the white paper
- Work in progress draft to be presented @ KIW in Feb 2019
- Get feedbacks from Virgo people
- First draft to be circulated @ April 2019 F2F
- Final version to be put for approval @ Aug 2019 F2F
How to proceed the discussion ?
- Make a skelton of the white paper first
- Dig deeper into each item with sub-groups
Other discussion
- Definitions of short term and longer term upgrades
- Short term: after O4 (~ in 5 years)
- Longer term: after O5-6 ? ~ in 10 years
- This should be discussed in FPC
- How to get funding should be discussed with relevant people (ICRR, senior people in collaborating countries, etc) in parallel with the white paper writing.
- Need to keep ICRR in the circle.
- Review (external/internal) of the white paper may be necessary before submitting to the KSC and EO for approval.
- The white paper should be updated with changing environment
How RDC should select KAGRA project R&Ds before the white paper is finalized ?
- RDC may be able to make interim approvals
These interim KAGRA project R&Ds should be checked against the white paper once it is ready
- Should be discussed more in the KSC session.
- RDC may be able to make interim approvals