Differences between revisions 253 and 344 (spanning 91 versions)
Revision 253 as of 2011-06-13 09:44:58
Size: 5549
Comment:
Revision 344 as of 2011-11-08 12:40:35
Size: 11476
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Line 4: Line 3:

.[[http://gw.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=335|Schedule for 2011]]

=== Next meeting: Face to face meeting on August 3-5, 2011  ===
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=335|Schedule for 2011]]

=== Next meeting: International collaboration meeting on Nov 8, 2011 ===
Line 10: Line 7:

== 40th(international): Nov. 8, 2011(Tue) 15:00~(JST) ==
[[LCGT/Meeting/weekly/20111108/EVO|EVO connection]] [ [[LCGT/Meeting/EVOen|help]] ]

Agenda

||Time||Topic||Speaker||
|| || || ||
||15:00-15:10||Project status report||Takaaki Kajita, presented by Kazuaki Kuroda||
||15:10-15:20||Report of SE office||Seiji Kawamura||
||15:20-15:30||Status of budget expenditure||Masatake Ohashi||
||15:30-16:20||Report of each sub-working group||chaired by Ichiro Nakatani||
||16:20-16:40||Re-scheduling of construction||Masaki Ando, planned speaker not confirmed||
||16:40-17:00||Determination of main mirror size||Seiji Kawamura||
||17:00-17:30||Special Topics and discussion||chaired by Seiji Kawamura||
|| ||1) New configuration for cryogenic mirror suspension||with NSF application status, Warren Johnson||
|| ||2) a status update on searches for long bursts||Maurice van Putten||


Files

 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=672 |Project report]] (Kajita)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=*** |SEO]] (Kawamura)
----
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=666 |DAT]] (Tagoshi (vice of Kanda))
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=670 |TUN]] (Uchiyama)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=645 |VAC]] (Saito)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=*** |LAS and MIR]] (Mio)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=*** |VIS]] (Takahashi)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=*** |CRY]] (Suzuki)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=*** |IOO]] (Telada)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=677|MIF]] (Aso)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=*** |IOO]] (Telada)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=676 |AOS]] (Akutsu)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=654 |DGS]] (Miyakawa)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=*** |AEL]] (Moriwaki)
----
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=668 |searches for long bursts]] (van Putten)


== 39th(domestic): October 17, 2011(Mon) 14:00~(JST) ==
[[LCGT/Meeting/weekly/20111017/EVO|EVO connection]] [ [[LCGT/Meeting/EVOen|help]] ]

Agenda

 1. Project reports( from management group, support group, chief meeting,SE-office, GWO) (Kajita, Miyakawa, Nakatani, Kawamura, Kuroda)
 1. Each Chief
 1. LIGO status(H.Yamamoto)
 1. Sapphire Bonding(K.Yamamoto)
 1. Others

Files

 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=648 |Project report]] (Kajita)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=647 |SEO]] (Kawamura)

----

 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=641 |22cm-Sensitivity]] (Somiya)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=653 |Layout]] (Miyoki)

----

 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=655 |DAT]] (Kanda)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=646 |TUN]] (Uchiyama)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=645 |VAC]] (Saito)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=651 |LAS and MIR]] (Mio, Hirose)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid= |VIS]] (Takahashi,De''''''Salvo)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=*** |CRY]] (Suzuki, Kimura)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=652 |MIF]] (Aso)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=*** |IOO]] (Telada)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=656 |AOS]] (Akutsu)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=654 |DGS]] (Miyakawa)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=657 |AEL]] (Moriwaki)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=658 |Web, Doc, Events]] (Miyoki,Miyakawa)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=649 |Project]] (Nakatani)
----

 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=659 |LIGO Status]] (H.Yamamoto)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=660 |Sapphire Bonding]] (K.Yamamoto)

----

 [[LCGT/Meeting/weekly/minute/20111017|Minutes]]
Line 14: Line 96:
 1. Projectからの報告(management, support, chief各会議,SEオフィス、重力波推進室) (梶田、宮川、中谷、川村、黒田)
 * 補助光学系作業班の新設について(中谷)
 * 各作業班の現状報告 (各チーフ)
 * 空洞掘削について(大橋)                   
 * 平成23年度予算執行について(大橋)
 * roadmap特別作業班の報告(安東)                         
 * Low frequency Band特別作業班の報告(宗宮)                       
 * LIGO支援要請と海外プロジェクトとの覚書締結状況(GEO)(黒田)                        
 * Program Advisory Board開催について(黒田)
 * 8月f2f meetingについて(宮川)
 * その他


Files
  . [[attachment:LCGT/Meeting/weekly/20110613/20110613_LCGT_Meeting.ppt|Laser & Mirror]] (Mio)


 1. Project reports( from management group, support group, chief meeting,SE-office, Gravitational wave office) (Kajita, Miyakawa, Nakatani, Kawamura, Kuroda)
 1. New sub-working group of Auxiliary Optics (Nakatani)
 1. Status report of each sub-working group (each Chief)
 1. Status report of excavation (Ohashi)
 1. About execution of budget of FY2011 (Ohashi)
 1. Report of roadmap special working group(Ando)
 1. Report of Low frequency Band working group (Somiya)
 1. Quarterly requests to LIGO and status of academic exchange withoverseas projects (GEO) (Kuroda)
 1. Preparation of Meeting of Program Advisory Board (Kuroda)
 1. About f2f meeting in August (Miyakawa)
 1. Others

Files

 . [[attachment:LCGT/Meeting/weekly/20110613/Project report-Kajita-110613.pdf|Project report]] (Kajita)
 . [[attachment:LCGT/Meeting/weekly/20110613/SE-Office_activity_20110613.pdf|SE-office]] (Kawamura)
 . [[attachment:LCGT/Meeting/weekly/20110613/110613 Collaboration Mtg.ppt|Organization Enhancement]] (Nakatani)
 . [[attachment:CollaborationMeeting_20110613.pdf|Data Analysis]] (Kanda)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=454|Tunnel]] (Uchiyama)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=455|Tunnel cost down plan]] (Uchiyama)
 . [[attachment:LCGT/Meeting/weekly/20110613/20110613_LCGT_Meeting.ppt|Laser & Mirror]] (Mio)
 . [[attachment:LCGT/Meeting/weekly/20110613/20110613_VI.pdf|Vibration Isolation]] (DeSalvo)
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=459|Main Interferometer]] (Aso)
 . [[attachment:LCGT/Meeting/weekly/20110613/20110613_digital.pdf|Digital]] (Miyakawa)
 . [[attachment:lcgt110613e.pdf|Roadmap]] (Ando)
 . [[attachment:LCGT-LF110613e.pdf|LCGT-LF]] (Somiya)
 . [[attachment:LCGT/Meeting/weekly/20110613/External_Review_Action_Status_20110613.pdf|PAB]] (Kawamura)

 . [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/LCGT/Meeting/Reviews|Review program]]

 . [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/LCGT/Meeting/f2f/2011Aug|F2F meeting program page]]

-----
Line 36: Line 135:
Line 37: Line 137:
 * Report of sub working groups
 * Budgetary report
 * Overview report of the Review B
 * Report of Road map and Bandwidth WGs
 * Current design of LCGT (optical interferometer)
 * Collaborations (Agreed MOU, IRSES application, Korean collaborators)
 * Establishment of System Engineering Office
 * Speakers of LCGT status talk in International conferences
 * Disclosing LCGT sensitivity curve on web page
 * Planned meeting of Program Advisory Board (member, date, agenda)
 * Others  
 1. Report of sub working groups
 1. Budgetary report
 1. Overview report of the Review B
 1. Report of Road map and Bandwidth WGs
 1. Current design of LCGT (optical interferometer)
 1. Collaborations (Agreed MOU, IRSES application, Korean collaborators)
 1. Establishment of System Engineering Office
 1. Speakers of LCGT status talk in International conferences
 1. Disclosing LCGT sensitivity curve on web page
 1. Planned meeting of Program Advisory Board (member, date, agenda)
 1. Others
Line 52: Line 152:
 * Sub working group reports  1. Sub working group reports
Line 61: Line 161:
  . [[http://gw.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=430|Analog]] (Moriwaki)
 * [[attachment:LCGT/Meeting/weekly/20110510/Budgetary outlays.pdf|Budgetary outlays]] (Ohashi)
 * [[attachment:LCGT/Meeting/weekly/20110510/External_Review_Action_Status_20110510.pdf|Summary of External Review and Current Status of Actions to Report]] (Kawamura)
 * Working group reports
  . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=430|Analog]] (Moriwaki)
 1. [[attachment:LCGT/Meeting/weekly/20110510/Budgetary outlays.pdf|Budgetary outlays]] (Ohashi)
 1. [[attachment:LCGT/Meeting/weekly/20110510/External_Review_Action_Status_20110510.pdf|Summary of External Review and Current Status of Actions to Report]] (Kawamura)
 1. Working group reports
Line 67: Line 167:
 * [[attachment:LCGT/Meeting/weekly/20110510/OCG.pdf|LCGT configuration]] (Somiya)
 * [[attachment:LCGT/Meeting/weekly/20110510/Collaboration110510.ppt|Collaboration with other projects]] (Kuroda)
 * [[attachment:LCGT/Meeting/weekly/20110510/110510 Collaboration Meeting.pptx|SYSTEM ENGINEERING OFFICE]] (Nakatani)
 * [[attachment:LCGT/Meeting/weekly/20110510/Speakers110510.ppt|Speakers of LCGT status talk at international conferences]] (Kuroda)
 * [[attachment:LCGT/Meeting/weekly/20110510/LCGT sensitivity limit.pdf|LCGT sensitivity curve on web]] (Miyakawa)
 * [[attachment:LCGT/Meeting/weekly/20110510/PAB_LCM110510.ppt|Program Advisory Board Meeting]] (Kuroda)



 1. [[attachment:LCGT/Meeting/weekly/20110510/OCG.pdf|LCGT configuration]] (Somiya)
 1. [[attachment:LCGT/Meeting/weekly/20110510/Collaboration110510.ppt|Collaboration with other projects]] (Kuroda)
 1. [[attachment:LCGT/Meeting/weekly/20110510/110510 Collaboration Meeting.pptx|SYSTEM ENGINEERING OFFICE]] (Nakatani)
 1. [[attachment:LCGT/Meeting/weekly/20110510/Speakers110510.ppt|Speakers of LCGT status talk at international conferences]] (Kuroda)
 1. [[attachment:LCGT/Meeting/weekly/20110510/LCGT sensitivity limit.pdf|LCGT sensitivity curve on web]] (Miyakawa)
 1. [[attachment:LCGT/Meeting/weekly/20110510/PAB_LCM110510.ppt|Program Advisory Board Meeting]] (Kuroda)

-----
Line 82: Line 180:
Line 85: Line 184:
 1. Double citizenship problem: Kazuaki Kuroda                  1. Double citizenship problem: Kazuaki Kuroda
Line 88: Line 187:
 1. Data sharing problem: Nobuyuki Kanda                1. Data sharing problem: Nobuyuki Kanda
Line 93: Line 192:
Line 96: Line 196:
 . [[http://gw.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=394|Tunnel]] (uchiyama)  . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=394|Tunnel]] (uchiyama)
Line 98: Line 198:
 . [[http://gw.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=395|SEMP]] (Nakatani)


----
 . [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=395|SEMP]] (Nakatani)

----
Line 103: Line 203:
 [[LCGT/Meeting/weekly/2009|Meetings in FY2008, 2009]]

[[LCGT/Meeting/weekly/2010|Meetings in 2010]]
 . [[LCGT/Meeting/weekly/2009|Meetings in FY2008, 2009]]
 . [[LCGT/Meeting/weekly/2010|Meetings in 2010]]
Line 108: Line 207:
----
----

LCGT collaboration meeting

Meeting schedule

Next meeting: International collaboration meeting on Nov 8, 2011


40th(international): Nov. 8, 2011(Tue) 15:00~(JST)

EVO connection [ help ]

Agenda

Time

Topic

Speaker

15:00-15:10

Project status report

Takaaki Kajita, presented by Kazuaki Kuroda

15:10-15:20

Report of SE office

Seiji Kawamura

15:20-15:30

Status of budget expenditure

Masatake Ohashi

15:30-16:20

Report of each sub-working group

chaired by Ichiro Nakatani

16:20-16:40

Re-scheduling of construction

Masaki Ando, planned speaker not confirmed

16:40-17:00

Determination of main mirror size

Seiji Kawamura

17:00-17:30

Special Topics and discussion

chaired by Seiji Kawamura

1) New configuration for cryogenic mirror suspension

with NSF application status, Warren Johnson

2) a status update on searches for long bursts

Maurice van Putten

Files



39th(domestic): October 17, 2011(Mon) 14:00~(JST)

EVO connection [ help ]

Agenda

  1. Project reports( from management group, support group, chief meeting,SE-office, GWO) (Kajita, Miyakawa, Nakatani, Kawamura, Kuroda)
  2. Each Chief
  3. LIGO status(H.Yamamoto)
  4. Sapphire Bonding(K.Yamamoto)
  5. Others

Files





38th(domestic): June 13, 2011(Mon) 14:00~(JST)

EVO connection [ help ]

Agenda

  1. Project reports( from management group, support group, chief meeting,SE-office, Gravitational wave office) (Kajita, Miyakawa, Nakatani, Kawamura, Kuroda)
  2. New sub-working group of Auxiliary Optics (Nakatani)
  3. Status report of each sub-working group (each Chief)
  4. Status report of excavation (Ohashi)
  5. About execution of budget of FY2011 (Ohashi)
  6. Report of roadmap special working group(Ando)
  7. Report of Low frequency Band working group (Somiya)
  8. Quarterly requests to LIGO and status of academic exchange withoverseas projects (GEO) (Kuroda)
  9. Preparation of Meeting of Program Advisory Board (Kuroda)
  10. About f2f meeting in August (Miyakawa)
  11. Others

Files


37th(international): May 10, 2011(Tue) 15:00~(JST)

EVO connection [ help ]

Agenda

  1. Project status report
  2. Report of sub working groups
  3. Budgetary report
  4. Overview report of the Review B
  5. Report of Road map and Bandwidth WGs
  6. Current design of LCGT (optical interferometer)
  7. Collaborations (Agreed MOU, IRSES application, Korean collaborators)
  8. Establishment of System Engineering Office
  9. Speakers of LCGT status talk in International conferences
  10. Disclosing LCGT sensitivity curve on web page
  11. Planned meeting of Program Advisory Board (member, date, agenda)
  12. Others

Files

  1. Project status report (Kajita)

  2. Sub working group reports
  3. Budgetary outlays (Ohashi)

  4. Summary of External Review and Current Status of Actions to Report (Kawamura)

  5. Working group reports
  6. LCGT configuration (Somiya)

  7. Collaboration with other projects (Kuroda)

  8. SYSTEM ENGINEERING OFFICE (Nakatani)

  9. Speakers of LCGT status talk at international conferences (Kuroda)

  10. LCGT sensitivity curve on web (Miyakawa)

  11. Program Advisory Board Meeting (Kuroda)


36th(domestic): March 7, 2011(Mon) 14:00~(JST)

EVO connection [ help ]

Agenda

  1. Project reports(management, support, chief): Takaaki Kajita, Osamu Miyakawa, Ichiro Nakatani
  2. Report of Review B: Seiji Kawamura
  3. Collaboration status with overseas projects (LIGO, Virgo, Shanghai Normal University, Sannio University, GEO): Kazuaki Kuroda
  4. Double citizenship problem: Kazuaki Kuroda
  5. Purchasing plan in FY 2011: Masatake Ohashi
  6. Milestone and roadmap: Masaki Ando
  7. Data sharing problem: Nobuyuki Kanda
  8. Schedule of meetings: Kazuaki Kuroda
  9. Others

Files


Past collaboration meeting



LCGT wiki top

LCGT/Meeting/weekly (last edited 2012-06-06 12:12:28 by OsamuMiyakawa)