1. Report of work of the last week and plan of work
- Vacuum of central area
 - Alignment, ETMY: Izumi
 - CAL
 - Cryo:
 
2. Schedule of ETMX installtion
- See the schedule at the commissioning top page.
 
3. Tasks or discussions
4. Phase2