Differences between revisions 1 and 25 (spanning 24 versions)
Revision 1 as of 2009-06-27 00:12:48
Size: 27
Editor: whitehole
Comment:
Revision 25 as of 2009-06-27 12:24:15
Size: 2679
Editor: whitehole
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
Describe CLIO/Tasks here. ||<#FFFF77>'''~+ [[CLIO/Meeting|/Meeting]] +~''' ||<#FFFF77>'''~+[[CLIO/Plans|/Plans]] +~''' ||<#FFFF77>'''~+[[CLIO/Tasks|/Tasks]] +~''' ||<#FFFF77>'''~+[[CLIO/Technicals|/Technicals]] +~''' ||<#FFFF77>'''~+[[CLIO/SiteInfo|/SiteInfo]] +~''' ||
||<#FFCCFF>'''~+ FindPage   +~'''||<#FFCCFF> '''~+ TitleIndex +~'''||<#FFCCFF> '''~+ WordIndex +~'''||<-2#FFCCFF>'''~+ HelpOnMoinWikiSyntax +~''' ||

Update: <<DateTime(2009-06-27T02:33:38+0900)>>

== Small Tasks & Schedules ==
|| Task Name || Responsible || STATUS || due ||
|| * [[CLIO/Tasks/CoilBobbin|コイルボビン]] ||(担当:内山) || 75% @ 2009/06/15 || 2009/09/End ||
|| * [[CLIO/Tasks/EndLight|エンド光]] ||(担当:三代木)|| 90% Inline End was done @ 2009/06/15 || 2009/06/End ||
|| * [[CLIO/Tasks/DigitalControl|デジタル化 1st phase]] ||(担当:宮川)|| 50% shopping + shipping || 2009/9/End ||
|| * [[CLIO/Tasks/Damping|ダンピング]] ||(担当:内山)|| 50% LSPI by Telada || 2009/9/End ||
|| * [[CLIO/Tasks/AlWireQ|純アルミ線Q値測定]] ||(担当:鈴木敏)|| 20% || 2009/9/End ||
|| * [[CLIO/Tasks/DigitalControl/AnalogFrontEnd2|デジタル化アナログフロントエンド・第2段]] ||(担当:辰巳)|| 10% || 2009/7/End ||
|| * RF intensity noise investigation ||(担当:我妻)|| || ||
|| * BS pendulum modification ||(担当:三代木)|| Under Design || ||
|| * ST pendulum modification ||(担当:三代木)|| Parts Ordered || ||
|| * [[CLIO/Tasks/Target|ターゲット板]] || (担当:宮川)|| 10% || 2009/8/End ||

== Pending Tasks ==
 * [[CLIO/Tasks/RecoilMass|リコイル・マス (担当:寺田)]]
 * MC WFS and beam orientation control (担当:我妻)
 * Arm cavity WFS or dithering (担当:我妻) 優先度:高Dithering 相当のシステムを早急に構築する必要あり。
 * Main suspension Y-stage installation (担当:内山)
 * [[CLIO/Tasks/CoilDriver|アクチュエイター雑音低減・第2段(担当:辰巳) コイルアクチュエイター効率の低減]]
 * Up-conversion noise investigation (担当:新井)
 * Shadow sensor (担当:辰巳、高橋)

== Past small Tasks ==
 * [[CLIO/Tasks/DigitalControl/AnalogFrontEnd|デジタル化アナログフロントエンド・第1段]](担当:辰巳) due: 2009/3/End
 * [[CLIO/Tasks/CoilDriver|アクチュエイター雑音低減・第1段]] (担当:辰巳) due: 2009/3/End
 * [[CLIO/Tasks/Done/BeamCenterJig|粗調ビームセンターリング]] (担当:新井) design due: 2009/1/8, deliver due 2009/1/End, preparation ends 2009/2/6

----
||[[CLIO|CLIO wiki Top]]||[[LCGT|LCGT wiki Top]]||

/Meeting

/Plans

/Tasks

/Technicals

/SiteInfo

FindPage   

TitleIndex

WordIndex

HelpOnMoinWikiSyntax

Update: 2009-06-27 02:33:38

Small Tasks & Schedules

Task Name

Responsible

STATUS

due

* コイルボビン

(担当:内山)

75% @ 2009/06/15

2009/09/End

* エンド光

(担当:三代木)

90% Inline End was done @ 2009/06/15

2009/06/End

* デジタル化 1st phase

(担当:宮川)

50% shopping + shipping

2009/9/End

* ダンピング

(担当:内山)

50% LSPI by Telada

2009/9/End

* 純アルミ線Q値測定

(担当:鈴木敏)

20%

2009/9/End

* デジタル化アナログフロントエンド・第2段

(担当:辰巳)

10%

2009/7/End

* RF intensity noise investigation

(担当:我妻)

* BS pendulum modification

(担当:三代木)

Under Design

* ST pendulum modification

(担当:三代木)

Parts Ordered

* ターゲット板

(担当:宮川)

10%

2009/8/End

Pending Tasks

Past small Tasks