||<#FFFF77>'''~+ [[CLIO/Meeting|/Meeting]] +~''' ||<#FFFF77>'''~+[[CLIO/Plans|/Plans]] +~''' ||<#FFFF77>'''~+[[CLIO/Tasks|/Tasks]] +~''' ||<#FFFF77>'''~+[[CLIO/Technicals|/Technicals]] +~''' ||<#FFFF77>'''~+[[CLIO/SiteInfo|/SiteInfo]] +~''' || ||<#FFCCFF>'''~+ FindPage +~'''||<#FFCCFF> '''~+ TitleIndex +~'''||<#FFCCFF> '''~+ WordIndex +~'''||<-2#FFCCFF>'''~+ HelpOnMoinWikiSyntax +~''' || |
Update: 2009-06-27 02:33:38
Small Tasks & Schedules
Task Name |
Responsible |
STATUS |
due |
* コイルボビン |
(担当:内山) |
75% @ 2009/06/15 |
2009/09/End |
* エンド光 |
(担当:三代木) |
90% Inline End was done @ 2009/06/15 |
2009/06/End |
(担当:宮川) |
50% shopping + shipping |
2009/9/End |
|
* ダンピング |
(担当:内山) |
50% LSPI by Telada |
2009/9/End |
(担当:鈴木敏) |
20% |
2009/9/End |
|
(担当:辰巳) |
10% |
2009/7/End |
|
* RF intensity noise investigation |
(担当:我妻) |
|
|
* BS pendulum modification |
(担当:三代木) |
Under Design |
|
* ST pendulum modification |
(担当:三代木) |
Parts Ordered |
|
* ターゲット板 |
(担当:宮川) |
10% |
2009/8/End |
Pending Tasks
- MC WFS and beam orientation control (担当:我妻)
- Arm cavity WFS or dithering (担当:我妻) 優先度:高Dithering 相当のシステムを早急に構築する必要あり。
- Main suspension Y-stage installation (担当:内山)
- Up-conversion noise investigation (担当:新井)
- Shadow sensor (担当:辰巳、高橋)
Past small Tasks
デジタル化アナログフロントエンド・第1段(担当:辰巳) due: 2009/3/End
アクチュエイター雑音低減・第1段 (担当:辰巳) due: 2009/3/End
粗調ビームセンターリング (担当:新井) design due: 2009/1/8, deliver due 2009/1/End, preparation ends 2009/2/6