20180921
Today's activities
Workers: Akutsu, K. Nagano, T. Tanaka, N. Fujii
- Shown in the above links and the below.
Next plan
- Repairing some damaged parts
- Replace the damages actuator coils.
- Lay cables for TMS and TMS-VIS
- Need to count the required number and length of the cables (on Sept 26??).
- Configure the digital models properly.
- Engage the logical channels and the assigned physical channels.
- Install geophones.
- Install TMS-VIS into the chamber.
- Install BRT on it.
Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.) See here.
Wanted!
- Tester!! lend from DGS or PEM??
- First contact to clean the side diameter of the optics.