Line 2: Line 2:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6269]]
Line 6: Line 7:
Shown in the above links and the below.
Line 10: Line 11:
 * Repairing some damaged parts
  * Replace the damages actuator coils.
 * Lay cables for TMS and TMS-VIS
  * Need to count the required number and length of the cables (on Sept 26??).
 * Configure the digital models properly.
  * Engage the logical channels and the assigned physical channels.
 * Install geophones.
 * Install TMS-VIS into the chamber.
 * Install BRT on it.
 * Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.) See [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9015|here]].

20180921

Today's activities

Workers: Akutsu, K. Nagano, T. Tanaka, N. Fujii Shown in the above links and the below. Preparation For TMSX Optic Installation part2

Next plan

  • Repairing some damaged parts
    • Replace the damages actuator coils.
  • Lay cables for TMS and TMS-VIS
    • Need to count the required number and length of the cables (on Sept 26??).
  • Configure the digital models properly.
    • Engage the logical channels and the assigned physical channels.
  • Install geophones.
  • Install TMS-VIS into the chamber.
  • Install BRT on it.
  • Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.) See here.

Wanted!

  • Tester!! lend from DGS or PEM??
  • First contact to clean the side diameter of the optics.