20180921

Today's activities

Workers: Akutsu, K. Nagano, T. Tanaka, N. Fujii Shown in the above links and the below. Preparation For TMSX Optic Installation part2

Next plan

  • Repairing some damaged parts
    • Replace the damages actuator coils.
  • Lay cables for TMS and TMS-VIS
    • Need to count the required number and length of the cables (on Sept 26??).
  • Configure the digital models properly.
    • Engage the logical channels and the assigned physical channels.
  • Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.) See here.

Wanted!

  • Tester!! lend from DGS or PEM??
  • First contact to clean the side diameter of the optics.