KAGRA Commissioning status at DET meeting
- Date : 2022/08/29
Overall schedule
- Overall schedule
- 9/2 Closed the beam duct and connected the vacuum pumps PRM - SRM
- 9/5 - 9/9 Closing the chamber with interferometer alignment
- This week(?) pumping down started if all work are done
- 9/20 - 9/22 OMC investigation for closing the chamber
- 8/26 Acceptance check ~SRM
- 9/13 - 9/16 Investigation of the ghost beam IFI and acceptance check