KAGRA Commissioning status at DET meeting
- Date : 2022/06/27
Overall schedule
- (In case of no trouble)
- 6/27 - EY : Repair the leak point and start the pumping down
- 6/20 - 7/1 Suspension commissioning Type-Bp
- 7/4 - 7/8 Interferometer commissioning
- 7/11 - 7/22 Suspension commissioning Type-B
- 7/25 - 7/29 Acceptance check ~PR2
- 8/1 - 8/5 Closing the center area ~PR2
- 8/8 - 8/19 (Including Obon) Acceptance check ~SRM
- 8/22 - 8/26 Closing the center area ~SRM
- 8/29 - 9/2 Leak test
- Mid size baffle installation (SR3, SRM)
- SRM replacement (Week of 7/4)
- ISS installation
- High power laser installation (Week of 7/4)
Progress of commissioning
- X arm commissioning
- End X IM 90K
- Investigation of the noise in the new oplev light source
- Y arm commissioning
- End Y : Leak done
- Center area commissioning
- Suspension health check Type-Bp's
- Mirror cleaning SR3 and SRM
- Investigation of the X-arm fiber noise cancellation
- We cannot keep control for the long time
- We have to fix it before starting the ALS DARM commissioning
- Study for installation of the new laser
- Alignment check by using heavy mass
Interesting data
- X arm cavity
- Both IR and GR
- Glitch investigation of the ITMX ADC
- Glitch investigation of the MN oplev light source
- Y arm commissioning
- Both IR and GR
- Center area commissioning
- Main IR
- ALS
- IMC (Input Mode Cleaner)
- ASC (Alignment Sensing and Control) done
- Long term stability check
- Beam power, beam position, oplev monitoring
- Glitch investigation
- Temperature dependence
- Relationship between PSL room
- With PEM channels
- (Hammering test?)
- OMC
- Invesigation will continue after closing the center area
- Because the BS is too fluctuate, it became difficult to investigate