KAGRA Commissioning status at DET meeting
- Date : 2022/07/11
Overall schedule
- (In case of no trouble)
- 7/11 - 7/22 Suspension commissioning Type-B and PR2
- 7/25 - 7/29 Acceptance check ~PR2
- 8/1 - 8/5 Closing the center area ~PR2
- 8/8 - 8/19 (Including Obon) Acceptance check ~SRM
- 8/22 - 8/26 Closing the center area ~SRM
- 8/29 - 9/2 Leak test
Mid size baffle installation (Final:SRM)
- ISS installation (Review 7/19)
- High power laser installation
Progress of commissioning
- X arm commissioning
- End X IM 83K
- Investigation of the noise in the new oplev light source
- Investigation of the TMSX beam shape
- Y arm commissioning
- End Y : Pumping down ongoing, there are still some leak, but we will continue the pumping down
- Center area commissioning
- Suspension health check Type-Bp's
- Oplev upgrade : Done
- PRM and PR3 mostly done, PR2 there are some homework
- Mid-size baffle : Partially done, need to move to final position
- Investigation of the X-arm fiber noise cancellation
Xarm : became stable -> Same treatment to Yarm
- Study for installation of the new laser
- Set inside the PSL room this week
- OMC investigation
- SRM replacement : Done
- Power budget : Done
- Beam profile measurement : This weeek
- Suspension health check Type-Bp's
Interesting data
- X arm cavity
- Both IR and GR
- Glitch investigation of the ITMX ADC
- Glitch investigation of the MN oplev light source
- Y arm commissioning
- Both IR and GR
- Center area commissioning
- Main IR
- ALS
- IMC (Input Mode Cleaner)
- ASC (Alignment Sensing and Control) done
- Long term stability check
- Beam power, beam position, oplev monitoring
- Glitch investigation
- Temperature dependence
- Relationship between PSL room
- With PEM channels
- (Hammering test?)
- OMC
- Invesigation will continue after closing the center area
- Because the BS is too fluctuate, it became difficult to investigate