- 221109
- Overall schedule
- All leak test at center area was performed
- OMC : In air, finalize will be performed this week.
- 22nd Nov: Close chamber, start pumping down
- TMSY : In vac, leak test done, opened the gate valve after 15th Nov.
- OMC : In air, finalize will be performed this week.
- ETMY cooling down will start from 15th Nov.
- All leak test at center area was performed
- Interferometer overall
- Initial alignment experiment
- 16:00- everyday
- PRMI lock trial
- Search the good alignment
- ADS engaged and alignment of the IMMT1,2 and PRM
- Search the good alignment
- FPMI lock succeeded
DARM(AS17), CARM(REFL45), MICH(REFL51->POP17)
Latest sensitivity klog22097
- Calibration evaluation
- Control filter optimization
- Interferometer characterization
- X arm commissioning
- End X IM 85K
- We will start the noise budget of the new oplev again
- OMC ASC using the Xend test mass
- Signal was detected in OMC PD
- Y arm commissioning
- IY duct shield cooling
- New high power laser
- PMC locked
- ISS
- Control loop done
- Characterization is ongoing
- ASC preparation
- Sensing matrix measurements
- Initial alignment experiment