KAGRA commissioning strategy
- Observation 24th May - 21st June
- CAL/DET week 17-24 May
- Status of 2023/04/19
- High prior work
- Alignment sensing and control
DARM control with better ASC latest
- Injection test and tapping PSL room
- Interferometer simulation
- Middle term
- Laser power increasing
- suspension control
- Data analysis of silent run
Silent run
- Latest
- Interesting topic
- Sudden dropping of IRX/IRY transmittance light
- Arm angular degree of freedom evaluation
- Oplev glitches
- Daytime / silent run
- 117 Hz noise
- Time variance
- Sensitivity breath
- Sudden dropping of IRX/IRY transmittance light