== 7/1 Skype Telecon == == 7/1 2016 Skype Telecon ==
Line 12: Line 12:
== 7/8 in Sogang University == == 7/8 2016 in Sogang University ==
Line 21: Line 21:
== 8/2 Skype Telecon ==

== 8/2 2016 Skype Telecon ==
Line 39: Line 41:
== 8/4 ==
 * Parts arrived and some mechanical parts were wrong, but now they are fixed. JGP will assemble today.
== 8/4 2016 Skype telecon ==
 * The parts arrived; some mechanical parts were found wrong; JGP have fixed them; JGP will assemble today.
Line 43: Line 45:
 * KK will check the algorithm and will let you know today.  * KC made the new algorithm without arc tangent. JGP will check the formulas with real data. KK will check if it can be done in the CDS system or not.
Line 47: Line 49:

== 10/6 2016 skype telecon ==

 * Target is Physics Letter A.
 * To check the calibration again with the peak areas and higher harmonics taken into account.
 * To check the drift data with the calibration factor.
 * To check if the oplev noise went down or not after we took the tiltsensor out.
 * For paper, KK and SK will write the intro part, and JGP will write the resulting part.
 * Email to Kanda-san (KSC) about the open data

=== paper contents ===
 * we could calibrate oplev using the tilt sensor
 * They agreed ok
 * Tiltsensor's dynamic range was much larger than oplevs
 * environmental perturbation to be improved


== 10/20 2016 Local metting (KK & SJ) ==
 * We do not understand the calibration factors (or the spectrum magnitudes) change between tilt sensors and oplevs
 * We will re-center the MCE oplev on Monday
 * An excitation peak will be inserted on MCE and see if the peak height change in time
 * We will have another local meeting on Wednesday morning.

== 10/26 2016 skype meeting ==
 * oplev noise floor change of the last measurement is most likely because of the tilt sensor installation
 * Jungyu will come to KAGRA and we will repeat the measurement
 * Windshields will be available thanks to Akutsu san in the next measurement
 * Schedule is not fixed yet

== 3/1 2017 skype meeting ==
 * 2nd visit klog list http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/IOO/TiltSensor/Documents2
 * How can we proceed with KAGRA open data regulations?
    * Kawamura-sensei will contact to Kanda-san
    * Then Kokeyama will ask to KSC board
 * Paper contents
    * Comparison between oplev and tiltsensor spectra
    * present a cal peak to show tiltsensor is properly seeing the mirror motion
    * dark/ADC noise limit of tiltsensor
 * How can we estimate the tiltsensor dark or ADC noise limit?
    * Junegyu and Kyuman will study
 * Target is Optics Letters
 * Make a rough draft by Niigata f2f meeting
 * Next call will be a few days before f2f meeting for the presentation there

== 4/13 2017 skype meeting ==

MinutesMeeting0413

== 6/13 2017 skype meeting ==

 * Junegyu edit the draft by 6/14 evening
 * Seiji & Keiko will read by the end of this weekend (6/18)

Meeting

Note_First_Meeting

7/1 2016 Skype Telecon

  • KC and JGP will consider closer for the optical configuration (please upload new info)
  • KK will check if we have all necessary components
  • KK, KC and JGP will discuss about the disital software in Seoul
  • SK and KK will meet in Kamioka for a preparation (8/10)
  • We'll have another skype meeting before the site work

7/8 2016 in Sogang University

  • JGP will prepare the drawing of the configuration (on the pylon optical table)
  • JGP will prepare the required circuits (signal amps).
  • For the online data taking and analysis, we will need a digital model and MEDM screens. JGP will prepare the initial concept of the digital software.
  • With the prepared concept, we will build the model and make MEDM screens during KC/JGP visit (~1day).
  • We noticed that the digital software cannot do arc tangent. We will consider to use an approximation.
  • As planned, KK and SK will collect the necessary hardware on 8/10 (DC power supply, 50m cable, cable adaptors, AA filter)
  • KK will let JGP know about the Dsub 9 pin assignment to connect to an AA filter.

8/2 2016 Skype Telecon

Preparation

  • JGP will get the drawing in a few days.
  • All the parts will arrive today. KC and JGP will carry them (no shipping).
  • JGP will assemble and test the circuits this week. Reports will be made next week.
  • Model and MEDM screens will be prepared with Kirii-kun on 8/10 as well as the first phase of the visit.
  • KC will think about the approximation formula of art tangent to use in the digital model.
  • SJ will submit the "tunnel entrance form" for the experiment.
  • KK will send the Dsub pin assignment today.
  • KK will find AA filter soon.

Other note

  • No IR laser beam during the experiment.
  • We have to check again about the safety lecture.

Next meeting

  • Next meeting will be 8/5 9:20 am. KK will call everyone on skype.

8/4 2016 Skype telecon

  • The parts arrived; some mechanical parts were found wrong; JGP have fixed them; JGP will assemble today.
  • The drawing of the optical table (python table) will be done today by JGP.
  • Test result of the setup will be emailed.
  • KC made the new algorithm without arc tangent. JGP will check the formulas with real data. KK will check if it can be done in the CDS system or not.
  • Check the safety rule.
  • SJ will submit the mine entrance form.
  • JGP will carry the clumps (which is to fix the sensor on the table).

10/6 2016 skype telecon

  • Target is Physics Letter A.
  • To check the calibration again with the peak areas and higher harmonics taken into account.
  • To check the drift data with the calibration factor.
  • To check if the oplev noise went down or not after we took the tiltsensor out.
  • For paper, KK and SK will write the intro part, and JGP will write the resulting part.
  • Email to Kanda-san (KSC) about the open data

paper contents

  • we could calibrate oplev using the tilt sensor
  • They agreed ok
  • Tiltsensor's dynamic range was much larger than oplevs
  • environmental perturbation to be improved

10/20 2016 Local metting (KK & SJ)

  • We do not understand the calibration factors (or the spectrum magnitudes) change between tilt sensors and oplevs
  • We will re-center the MCE oplev on Monday
  • An excitation peak will be inserted on MCE and see if the peak height change in time
  • We will have another local meeting on Wednesday morning.

10/26 2016 skype meeting

  • oplev noise floor change of the last measurement is most likely because of the tilt sensor installation
  • Jungyu will come to KAGRA and we will repeat the measurement
  • Windshields will be available thanks to Akutsu san in the next measurement
  • Schedule is not fixed yet

3/1 2017 skype meeting

  • 2nd visit klog list http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/IOO/TiltSensor/Documents2

  • How can we proceed with KAGRA open data regulations?
    • Kawamura-sensei will contact to Kanda-san
    • Then Kokeyama will ask to KSC board
  • Paper contents
    • Comparison between oplev and tiltsensor spectra
    • present a cal peak to show tiltsensor is properly seeing the mirror motion
    • dark/ADC noise limit of tiltsensor
  • How can we estimate the tiltsensor dark or ADC noise limit?
    • Junegyu and Kyuman will study
  • Target is Optics Letters
  • Make a rough draft by Niigata f2f meeting
  • Next call will be a few days before f2f meeting for the presentation there

4/13 2017 skype meeting

MinutesMeeting0413

6/13 2017 skype meeting

  • Junegyu edit the draft by 6/14 evening
  • Seiji & Keiko will read by the end of this weekend (6/18)

KAGRA/Subgroups/IOO/TiltSensor/Meeting (last edited 2017-06-13 15:32:24 by KeikoKokeyama)