Size: 2352
Comment:
|
Size: 2377
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
= Upgrade IMC for O4 = | = Upgrade the input mode cleaner (IMC) for O4 = |
Upgrade the input mode cleaner (IMC) for O4
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
Links to knowledge
- Slack channel: #imc-upgrade
Beam position on the shield of the IMC Type-C: https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12114
IMC Type-C shield install procedure: https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12382
Installing the shields and BeamDumps for IMC https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11636
The following are somewhat old but maybe useful to trace what were going on at that time.
Locations of beam dumps in vacuum chambers of iKAGRA https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3900
主にAOSの立場から見たiKAGRAインストールおよびコミッショニング作業での課題と教訓 https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5202
IOO(MCF, MCE, IFI, IMM) 3D drawing (just for working) https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2507
About MCe transmission port https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2640
About MCo transmission 2 beam https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2605
About the laser guide duct https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2518
Related areas
MCF, MCE
Task list
Note: some of the tasks can be done in parallel.
- Attach black shielding around the MCi, MCo, and MCe suspensions for mitigate stray light
- Relocate the connector plates of these suspensions.
- Tame the electric wires from the coil bobbins.
- Put beam dumps in the MCE and MCF chambers.
- Confirm the position of POM1
- Attach the beam dump to POM1
- Confirm the position of a mirror (and the size) for MCo oplev
- Confirm each suspension can work very well (acceptance test)
- Alignment sensing control.
- Confirm no clipping of the beams.
- Confirm the laser beams are not hitting strange things such as coil wires and so on.
- Make the final 3D model inside of the MCF and MCE chambers before closing them.