Type-A Meeting on 2018/4/3
2018/4/3 13:00 - @Kamioka
Participants: Takahashi, Sato, Ishizaki, Okutomi
Minutes
X-front
- Repairing of F3
- Mounting of F1 with the wire again
- Cabling between the F2 and the F1 again
- Tuning of F1
- Lifting down of F2
X-end
- Fastening of bolts for the chamber
Type-A Meeting on 2018/3/27
2018/3/27 13:00 - @Kamioka
Participants: Takahashi, Sato, Ishizaki, Okutomi
Minutes
X-front
- Cabling in F1
- Mounting of F1 with the wire
- Tuning of F1
- Cabling between the F2 and the F1
- Lifting down of F2
X-end
- 3/26-27: Adjustment of height of the filters
Type-A Meeting on 2018/3/20
2018/3/20 12:40 - @Kamioka
Participants: Takahashi, Sato, Ishizaki
Minutes
X-front
- Lift down the F3
- Go to the F1 stage (FR, small hexagon, receptacle)
X-end
- 3/19: Pushing down of keystone in the TF
- 3/20: Connection of cables
- 3/21: Hanging of CP
Type-A Meeting on 2018/3/14
2018/3/14 12:40 - @Kamioka
Participants: Takahashi, Sato
Minutes
X-front
- Tuning of F2
- Check of FR
- Cabling around F2 and check of connection
- Prearation of F1
- Lifting down of F3
X-end
- 3/19: Pushing down of keystone in TF
- 3/20: Hanging of CP
- 3/21: Connection of cables
Type-A Meeting on 2018/3/5
2018/3/5 13:20 - @Kamioka
Participants: Takahashi, Sato, Okutomi
Minutes
X-front
- F3 stage (Transfer function, Test of SM).
- Preparation for the F2 (end plate、side stopper、side plate、small hexagon、cables).
X-end
- 3/5: Measured chamber height. Vented, Open chamber
- 3/6: Dismount DP
- 3/7: Install wire with cabling
Y-end
- Under cooling.
Type-A Meeting on 2018/2/27
2018/2/27 12:40 - @Kamioka
Participants: Takahashi, Sato, Ishizaki, Okutomi
Minutes
X-front
- F3 stage (Cabling, Tuning again, Transfer function, Test of SM).
- Preparation for the F2.
X-end
- ~3/5: Okutomi experiments
- 3/5: Measure chamber height. Start vent
- 3/6: Open chamber, Dismount DP
- 3/7~: Start cabling
Y-end
- Under cooling.
Type-A Meeting on 2018/2/20
2018/2/20 13:00 - @Kamioka
Participants: Takahashi, Sato, Ishizaki, Okutomi
Minutes
X-front
- Add FR blade. Tune the BF again.
- Go to the F3 stage (F1 tuning, cabling).
X-end
- ~3/2: Okutomi experiments
- 3/5: Measure chamber height. Start vent
- 3/6: Open chamber, Dismount DP
- 3/7~: Start cabling
Y-end
- Under cooling.
Type-A Meeting on 2018/2/13
2018/2/13 13:00 - @Kamioka
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
X-end
- ~3/2: Okutomi experiments
- 3/2: Start vent
- 3/5-6: Open chamber, Dismount DP
- 3/7~: Start cabling
Y-end
- Under cooling. Keep monitoring.
X-front
- Short rod was delivered.
- Install DP and BF.
- Prepare for LVDT driver. Use temporary power supply.
- Prepare for SM driver.
- Start assembly of F3 stage (connector plates, small hexagon, ...)
- Ordered additional FR parts. Delivery will be on 2/19.
- Check strength of FR blade.
Type-A Meeting on 2018/1/16
2018/1/16 13:00 - @Kamioka
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
X-end
- Solved some problems (coil driver for BF damper, vacuum gauge).
Y-end
- Checked the connector at BF.
- Preparation for evacuation (1/17 12:30 Meeting).
- Evacuation will be started in the 19th morning.
X-front
- Start the assembly of DP.
- Open the top chamber.
- Combine the PI for SRM.
Procurement
- PTFE cabels was delivered.
- Ballast ring will be delivered on 22nd.
- Hand pallet was ordered.
Type-A Meeting on 2018/1/9
2018/1/9 13:00 - @Kamioka
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
X-end
- Leak point check.
- Transportation (Footholds, chain blocks)
Y-end
- Preparation for evacuation (1/10 12:30 Meeting)
- Transportation (Protection net, DP)
Center
- Top chamber open (dry air is necessary)
- Transportation to 2F (from needed items)
- Assembly of PI for IXV, IYV, SRM.
Procurement
- Peek Dsub connectors
- Short rod for DP
Type-A Meeting on 2017/11/7
2017/11/7 13:00 - @NAOJ
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
Status
- Control test in X-end: Measurement of TFs was finished. Damping test is planed.
- Assembly of BFs: Finished and shipped from the clean room. FRs for SF will be assembled.
- Preparation of ACCs: Six units are available. One driver needs to be modified.
Schedule
- 11/13 Shipping in Akeno and Mitaka. Preparation for the center area.
- 11/14 Delivery in Kamika at 9:00. Transortation of the bridge frame.
- 11/17 Lifting of the items by MESCO.
- 11/15-17 Replacement of cables in X-end.
- 11/27-28 Connection to the cryo-payload in Y-end. Check the delivery of rods and junction boxes.
- Assembly of the pre-isolator for SRM is postponed to December.
Procurement
- PEEK Dsub connector (Takahashi), ordered
- Receptacle (Takahashi), ordered
- Small hexagon (Takahashi), ordered
- Counter weight (Takahashi)
- Stepping motor (Takahashi)
- Cable assembly (Sato)
- Bottom anchor (Sato)
- ACC adapter (Sato), ordered
- Touch sensor (Sato), ordered
- Rack (Ishizaki), order on 11/13
- Collar (Sato)
Next meeting: 2017/11/14 13:00
Type-A Meeting on 2017/10/31
2017/10/31 13:00 - 13:30 @NAOJ
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
Status
- Control test in X-end: Start evacuation on 11/1.
- Assembly of BFs: Finish on 10/31, shipping is within this week,
- Preparation of ACCs: 6 units are working, some modification for the drivers are going.
Schedule
- 11/13 Shipping in Akeno and Mitaka.
- 11/14 Delivery in Kamika at 9:00, Preparation for the center area, Transortation of the bridge frame.
- 11/17 Lifting of the items by MESCO
- Assembly of the pre-isolator for SRM is postponed to December.
Procurement
- PEEK Dsub connector (Takahashi)
- Receptacle (Takahashi)
- Small hexagon (Takahashi)
- Counter weight (Takahashi)
- Stepping motor (Takahashi)
- Cable assembly (Sato)
- Bottom anchor (Sato)
- ACC adapter (Sato)
- Touch sensor (Sato)
- Rack (Ishizaki)
- SUS sheets (Ishizaki)
Next meeting: 2017/11/7 13:00
Type-A Meeting on 2017/1/17
2017/1/17 13:00 - 14:00 @Kamioka
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-2 Simulation (Okutomi)
- Report was postponed to the next meeting.
- Top chamber was disconnected to repare the leaked part.
- It was expensive to make new boxes for packing the pre-isolators. We reuse the boxes for IP,
- Will be removed from the large clean room on 23rd.
- Will be delivered on 18th.
- Will be delivered on 20th.
- Plan of cable arrangement was shown.
- Still discussing about tagging.
- Start from covering the floor by stainless steel sheet.
- Send small tools used in ATC.
Next meeting: 2017/1/24 13:00
Type-A Meeting on 2017/1/10
2017/1/10 13:30 - 14:30 @Kamioka
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-2 Simulation (Okutomi)
- Report was postponed to the next meeting.
- EYV system will be vented in this week.
- Asking a quotation of modified parts for yaw motor slider.
- Asking a quotation of boxes to pack the pre-isolators.
- Will be delivered on 18th.
- Will be delivered on 20th. About 10 secondary coils come later.
- Order spare M12 stop screws.
- Aging for 3.3m rod is not available.
- The second transportation for EQ stop parts and tools is scheduled in 10-11th from Mitaka to Kamioka by Kamoshida, on 12th to Y-end by Kamioka-kogyo, and on 13th to 2F by MESCO in January.
- Stainless sheets were delivered.
- Send small tools used in ATC.
Next meeting: 2017/1/17 13:00
Type-A Meeting on 2016/12/27
2016/12/27 13:00 - 14:30 @Room 210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Tomograph is necessary.
- Designed control model will be reported in the next meeting.
- The top chamber was connected on 20th. The piston system was modified, so the pre-isolator was not installed. Two cross tubes were assembled.
- Assembly of two TFs for SR was finished.
- Stepping motors for yaw will be assembled later.
- A small crack was found on the blade. The plating has come off?
- Tested a combiner prototype. We asked AEL group the combiner modules with the tested parameter.
- Design of bottom anchor was approved. Ask companies a quotation.
- Checked delivered parts at the site on 22nd.
- The second transportation for EQ stop parts and tools is scheduled in 10-11th from Mitaka to Kamioka by Kamoshida, on 12th to Y-end by Kamioka-kogyo, and on 13th to 2F by MESCO in January.
- Prepare the shipping on 4-5th January.
- Ordered the net and the frame.
- Delivered.
- All of parts were delivered.
- Extensions and stainless sheet are necessary.
- Make a wire cramp for cryo-payload.
- Order the fiber scope.
- List up small tools.
Next meeting: 2017/1/10 13:00
Type-A Meeting on 2016/12/13
2016/12/13 13:00 - 15:00 @Room 210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-2 Simulation (Okutomi)
- Making the model for the digital control.
- Connection of the top chamber is scheduled in 21st-22nd. TMP, cone bellows, feedthroughs, and cross tubes will be assembled.
- Started assembly of TFs for SR.
- IPs for SR will be moved to the clean room on 13th.
- Two BFs were transported to Kamioka with the IPs.
- Magnets were delivered.
- Design of bottom anchor was shown. 4 brackets prop up the wall of chamber.
- Remain parts were delivered on 12th.
- The cramp was ordered.
- IP, Filters, and EQ stop parts were transported in 7-8th.
- The second transportation was scheduled in 10-11th for Kamioka and 12-13th for Y-end in January.
- The idea of cable tag was shown. Al plate with tag is fixed to each cable by PEEK filament.
- Pre-assembly of parasol was tried.
- The bridge was ordered. The parts were delivered on 13th.
- The company people on the fiber scope will come to NAOJ on 14th.
Next meeting: 2016/12/27 13:00
Type-A Meeting on 2016/11/29
2016/11/29 13:00 - 14:30 @Room 210
Participants: Takahashi, Ishizaki, Sato
Minutes
- 2-1 Setting of top chamber (VAC)
- TMP comes from NAOJ. It will be attached on 21st December.
- 4x2 stepping motors were checked.
- Connection of LVDT for one set of IP was ok.
- Primary coil for vertical of the other set has disconnection.
- Packing of two PIs is on 30th.
- Shipping is on 1st December. Ishizaki will receive them on 2nd at the KAGRA site.
- Two BFs will be transported with IPs.
- Magnets should be ordered.
- Some parts have been delivered on 17th. Remain parts will be delivered on 12th December.
- Ordered. The first set will be delivered by 20th January. The installation is started on 25th.
- Found small clamp for the damper wire.
- Ask companies a quotation.
- The first transportation is scheduled in 7-10th December.
- The second transportation is scheduled after 10th January.
- The parts will be delivered. We need pre-assembly for receiving inspection.
- Design of bridge was fixed.
- Ask the company about focus length of the fiber scope.
Next meeting: 2016/12/6 13:00
Type-A Meeting on 2016/11/22
2016/11/22 10:00 - 11:30 @Room 210
Participants: Takahashi, Ishizaki, Sato
Minutes
- 0-2 Simulation (Okutomi)
- (to be reported)
- Cleaning will be finished by 6th December.
- Shipping of two PIs is scheduled on 1st December. Ishizaki will receive them on 2nd at the KAGRA site.
- Two sets for SR was transported from Akeno on 21st.
- On going.
- Two BFs will be transported with IPs.
- Fixed the drawings for the coil bobbin.
- One set of receptacles will be manufactured as new ones.
- Set collar is useful for center wire.
- It is necessary to hold the load of 7-8kg.
- Divided the transportation by the company by 2 times.
- PIs will be transported after 10th December.
- Only tube of connection pin is necessary.
- Parasol is independent in the frame order.
- Bridge consists of Misumi frame.
- Some ideas on fiber scope were shown by Sato.
Next meeting: 2016/11/29 13:00
Type-A Meeting on 2016/11/15
2016/11/15 13:00 - 14:30 @Room 210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Inconsistency of 1mm in the total length of EQ stop was solved.
- Sharing the parameters with Miyamoto by Google spreadsheet.
- Made the real time model, but not "make" and "build" yet.
- Made master model of PI and GASF for Type-B.
- Next work is on 16th.
- Shipping of two PIs was scheduled on 1st December. Ishizaki will receive them on 2nd at the KAGRA site.
- Two sets for SR will be transported from Akeno on 21st.
- Measurements of 6 units were finished. 2 of 6 have low performance.
- Measurements of remained 3 units are postponed.
- On going.
- Two BFs were packed. They will be transported with IPs.
- Open bidding was on 9th.
- There is a meeting with the company on 15th.
- Pending.
- Consulted on interface with AEL members.
- The sensors were delivered.
- It is difficult to keep high tension.
- Think a clamp so that it can keep the position without slip down.
- The review was held on 4th.
- Asking a company transportation to the Y-end during 7-13th December.
- Footholds, table, chain blocks, and lifter will be ordered soon.
- Still asking some companies a quotation for the hoist tool.
Next meeting: 2016/11/22 10:00
Type-A Review on 2016/11/4
http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5855
Type-A Meeting on 2016/11/1
2016/11/1 13:00 - 13:30 @Room 210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Updated 2D assy. drawings. The total length of EQ stop is inconsistent by 1mm.
- Make digital control model of Type-A system.
- New bolts for the yoke were delivered.
- The top filter was mounted onto the IP.
- The shaft screw of motor was not matching to the slider for fishing rod. New shafts were delivered.
- LVDT driver and DC power supply are necessary.
- Next measurements is planed on 7-9th.
- Packing of two BFs was postponed.
- Open bidding is on 9th.
- Asking the company a quotation.
- The review is held on 4th. Draft document was previewed and discussed.
- Transportation to Kamioka is on 25th.
- Transportation to the Y end is on 30th.
- Go to the order after the review.
Next meeting: 2016/11/15 13:00
Type-A Meeting on 2016/10/25
2016/10/25 13:00 - 14:00 @4th meeting room
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Made 2D assy. drawings (cross section).
- Make Type-B model too.
- Finish the construction and cleaning by the end of November.
- Leak test is planed from 13th to end in December.
- Magnets were replaced.
- Broken bolts were removed. Ordered new bolts.
- If the bolts arrived, go to assembly on 26th.
- The results of measurement for 3 ACCs at the KAGRA site should be reported on 28th.
- Next measurements is planed on 7-9th in November.
- Pack two BFs on 26th.
- Proposal was submitted. It will be circulated.
- Design combiner by the end of November.
- If no assembly work for pre-isolaotr, go to test on 26th.
- Hirata is making 2D drawings.
- The review is held on 4th November. Make drawings for the document.
- T3 is available in arm.
- Cover items at for passing through IYC and EYC.
- Consulting with a company. It is difficult to use polycarbonate sheet of 2mm.
- Kimura-san will order the floor plate around cross tube.
- Price of hand lifer made of stainless steel is more than 0.3MYen.
- Fiber scope is useful, but the size is limited.
Next meeting: 2016/11/1 13:00
Type-A Meeting on 2016/10/18
2016/10/18 13:00 - 14:30 @Room 210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Made 2D assy. drawings (cross section).
- Had the workshop with Miyamoto on 6-8th. Made the model including the cryo-payload.
- Delivered.
- IP and TF were carried into the clean room in 6-7th.
- Poles to support upper TF were collapsed in the box. Some screws and magnets for york are broken.
- Started assembly of pre-isolator on 19th.
- Measured the sensitivity of 3 ACCs at the KAGRA site in 12-14th.
Measured sensitivities were 10-10~10-9m/rtHz.
- Finished the assembly of two BFs. They will be packed on 26th.
- The bidding was announced on 14th. Open bidding is on 9th November.
- Designing combiner.
- Ordered.
- Asked ATC redesign of the head with safety margin of 2.
- Hirata is making 2D drawings.
- The review is held on 4th November.
- Designed the hoist tool using 500kg chain blocks. Consult with a company.
- Order 3 (high) and 2 (low) sets of foot hold.
- Kimura-san is considering floor plate around the cross tube.
- Total load for the floor comes from the weight of carry lifter and dummy payload.
- Consider lope to avoid falling tools.
- Sato suggested cable tab.
Next meeting: 2016/10/25 13:00
Type-A Meeting on 2016/10/4
2016/10/4 13:00 - 14:30 @Room 210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Adding F1 damper and IP base.
- The work with Miyamoto is planed in 6-8th.
- Held on 3rd. Used the fork lift.
- Inspection of crane in the large clean room is held on 5th.
- Carry IP and Tf into the clean room in 6-7th.
- Final test is planed at the KAGRA site on 12-14th.
- Drivers and additional 3 units should be sent within this week.
- Assembling the 2nd unit.
- Asking quotation. Some questions are coming from the company.
- Test report was uploaded.
- Need holes for cables on the shild plate.
- The next test will be held on 5th.
- Order soon.
- We concluded that the load during crane operation is not over 2G.
- We should take care of misoperation.
- The review is scheduled in early November.
- Crawler was prepared at the site.
- Designing now.
Next meeting: 2016/10/18 13:00
Type-A Meeting on 2016/9/20
2016/9/20 13:00 - 14:30 @4th meeting room
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Adding the model of BF damper and replacing the model of BF by Hirata.
- Asking the company the model of IP base.
- The next meeting with Miyamoto has not been scheduled yet.
- Akeno on 3rd October.
- The place became the large clean room in ATC.
- Access from the east door of TMT building is available.
- Final test is planed at the KAGRA site on 28-30th.
- Making the specification document. Add inspection items, baking, S/N, gluing.
- Measured the actuator Efficiency: 76mN/A.
- Measured the position dependence of the efficiency.
- Thermal load of 1W is predicted. PEEK is still acceptable.
- Had kick off meeting with the company person on 16th.
- Length of rods was changed.
- Tuned the weight of dummy payload for BF.
- The next test will be held in October.
- Ask quotation.
- The safety margin in Virgo was 2.
- Show head size roughly.
- Start design.
- Short holds (~1m) are necessary too.
Next meeting: 2016/10/4 13:00
Type-A Meeting on 2016/9/13
2016/9/13 13:00 - 14:30 @Room210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Made assy. model with the chamber. Add the IP base to the mode.
- Making a model of cryo-payload independently.
- Cleaning around EYV will be started on 5th December.
- The place has not decided yet.
- Measured additional 3 units. The last i unit has a different connector.
- Started on 7th.
- Made the drawings of parts. Make assy. drawings.
- Showed design of the cabling and the connector plate.
- The 1st specification document should be prepared by 16th.
- Set up the bench for actuator test using damping rods and an acrylic table.
- Measured the LVDT. Efficiency: 575V/m, Sensitivity: 10^-8m/rtHz
- Open bidding is on 13th.
- The next setup consists of SF-BF-DP with M12 receptacle.
- The work is planed on 14th.
- Ask quotation for sensors with short cable.
- New design and test for strength is on going.
- CFRP is available as material?
- Considering the type used in ATC, which is ready made and folded.
Next meeting: 2016/9/20 13:00
Type-A Meeting on 2016/9/6
2016/9/6 13:00 - 14:00 @Room310
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- This is the first priolity.
- Consulted with Miyamoto at Hongo on 1st. The information was shared.
- Make a model of cryo-payload independently, and compare each other.
- It is difficult to insert the cone bellows later.
- The pre-isolator will be put on the cone bellows at the time of leak test.
- The place has not decided yet. Scheduling is pending.
- Other 3 units were taken on 31st.
- Ni plating was finished. Some blades were lusterless. They will be plated again.
- From 7th.
- The support for primary coil and the hole position in coil bobbin will be modified.
- Coil winding and assembly of the prototype was finished.
- The test will be started in this week.
- The length of rods was changed.
- Open bidding will be on 13th.
- The next setup consists of SF-BF-DP with M12 receptacle.
- It is necessary to disassemble the EQ stop once. The work is planed on 7th.
- Ask quotation for sensors with long cable.
- Calculation and test for strength is on going.
- The shape of head should be modified. Max. diameter is 8mm.
- 100kg crawler is in consideration.
- From 20th in January.
- Items will be hung by 3 chain blocks.
- 1.5t chain block is in consideration, but maybe too large.
- Stainless plate is necessary on the fine floor.
- It is difficult to prepare for a hand lifter with large foot width.
Next meeting: 2016/9/13 13:00
Type-A Meeting on 2016/8/30
2016/8/30 13:00 - 15:00 @Room210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- This is the first priolity.
- Showed the yaw spectrum of the BF.
- Requirement for dynamic range has not been shown yet.
- Requirement for sensor is 10^-10m/rtHz, if the BF is controlled all the time.
- Meet Miyamoto to discuss on the cryo-payload on 1st September.
- Leak test will be postponed for half of month due to delay of cooling test.
- Takahashi had a meeting on the place with Flaminio and Aso on 25th.
- The place has not decided yet. Still negotiating.
- Calibration is postponed to the end of September.
- Other 3 units will be taken on 31st.
- From September.
- Amount of lift-up should be decided before the design of support ring.
- Rotational position of BF cover should be fixed.
- How to keep cables to cryostat? Connected or disconnected.
- Bracket was modified. The lowest frequency was 120Hz.
- Shape of bobbin depends on the prototype test.
- Connectors for coils are mounted on the support frame.
- Amplitude of oscillator was increased in 5 times. Efficiency became 5 times.
- Test of sensor was finished. Test of actuator has not been yet.
- Two companies bid. Technical examination will be held.
- Takahashi will make the test plan and Ishizaki will make the schedule.
- Keep one day per week at least for the test.
- The test circuit will be used in installation.
- Final circuit is necessary by July in 2017.
- Consult with AEL.
- Calculation and test for strength is necessary for all rods.
- If the strength is not large enough, the shape of head should be modified.
- The rod for cryo-payload can stay in the cryostat.
- Plates for connectors should procured with the items on BF damping.
- Add 20 plates for Type-Bp.
- Added as new items.
Next meeting: 2016/9/6 13:00
Type-A Meeting on 2016/8/23
2016/8/23 13:00 - 14:30 @Large meeting room
Participants: Takahashi, Sato, Okutomi
Minutes
- 0-2 Simulation (Okutomi)
- Calculating requirement for actuators and sensors.
- Estimated the case using F7 LVDT, and the case using actual LVDT.
- Summarized within today, and present in the f2f meeting.
- Leak test should be performed in December, 2016.
- Takahashi had a meeting on the place with Flaminio and Aso.
- The place has not decided yet. Next meeting will be held on 25th.
- Measured 6 sets were transported to Kamioka.
- Calibration is planed at the site from 5th in September.
- 6 sets were transported to Kamioka on 17th.
- Structure analysis was applied to the model.
- Bracket of primary coil: 102Hz, bracket of secondary coil: 124Hz, including ring (t=20mm): 100Hz
- The shape of adjustment hole will be changed from long circle to large circle.
- Designed adapter for primary coil.
- Considering set up for actuator.
- Coil bobbins of prototype were delivered on 19th.
- Amplitude of oscillator should be larger (now 1V).
- The bidding was announced on 17th. Two companies had contact.
- Suspension test using maraging wires was performed on 18th.
- This item should be added.
- Protection net, hoist tool, foot hold, handling tool were added as new items.
Next meeting: 2016/8/30 13:00
Type-A Review on 2016/8/10
http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5516
Type-A Meeting on 2016/8/9
2016/8/9 13:00 - 14:00 @Room210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Made the model of EQ stop.
- Calculated coupling to the yaw mode assuming asymmetry of 1mm and 3mm. The result was linear.
- Updating the calculation (Next by 8/10).
- Additional 3 sets have not been extracted yet.
- Delay.
- The 6th set will be finished on 10th.
- Design of frame and jigs was progressed.
- We consulted with a company on procurement.
- Measured responce of LVDT sample. The signal was linear in 20mm range.
- Found phase noise at the level of 10^-6m/rtHz.
- Bracket for prototype is necessary.
- Made 2D drawings for the bidding.
- Tolerance and surface accuracy should be indicated.
- The tolerance for the rods with the same length must be less than 0.2mm.
- The specification document and drawings should be sent by the 12th.
- Height of base was 56mm. Changed to 50mm.
- The length of Hook was reduced.
- The document will be revised by the review.
- Total 20 system.
- 7 interfaces are necessary.
Next meeting: 2016/8/16 13:00
Type-A Meeting on 2016/8/1
2016/8/1 13:00 - 16:00 @Room210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- Made the model of EQ stop and pre-isolator.
- Each filter is placed at the side stopper.
- The IP is put on the top plate directly at present, but a gap is necessary.
- Take account of stretch of the wires.
- Introduction of coupling to the yaw mode was wrong in the last calculation.
- Updating the calculation.
- The lighting is made by the LED inside the booth.
- The assembly work will be started on 30th August at the KAGRA site.
- Additional 3 sets have not been extracted yet.
- The 5th set was finished.
- The thermal process for the blades was finished.
- The plate for damper is independent of EQ stop frame.
- Each LVDT has position adjustment.
- Set the test bench for LVDT sample at ATC lab.
- Making 2-pin lemo cables.
- A summer student will join to the test.
- Made 2D drawings for the bidding.
- The date for the announce of bidding is the 17th August.
- The specification document and drawings should be fixed by the 10th.
- Tested connection and lift down of the EQ stop prototype on 27th July.
- Set at 5mm under of each filter.
- The shape of jigs will be modified with thick base.
- The bottom should be a breadboard with 50mm interval.
- The first draft was shown and discussed.
- The height setting for each filter is important.
Next meeting: 2016/8/9 13:00
Type-A Meeting on 2016/7/26
2016/7/26 13:00 - 14:20 @Room210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assy. (Ishizaki)
- The modeling of EQ stop was almost finished.
- The model of chamber will be added to it.
- Calculated the effect due to actuation point for BF.
- Noise will be induced to the actuators taking account of measured LVDT.
- Design of suspended booth was shown.
- The lighting is OK?
- Decision on the working place is under negosiation.
- From August 30.
- Additional 3 sets will be taken by the end of July.
- The 4th set is on going.
- Ordered.
- Blades are in the thermal process.
- Made drawings for LVDT prototype.
- Make drawings for EQ stop side.
- Set the sample from VIRGO in the 20m lab.
- Making connector cables.
- Micrometer stage and some jigs are necessary.
- Made 3D model and 2D drawings.
- Bottom support for the dummy payload is necessary.
- Gap of the side stopper should be 10mm.
- Adjustment of top ring position is not necessary.
- Outer diameter of the plate was reduced on 20th.
- The shape of jigs was modified with 30mm in height.
- Gutter for cables is necessary.
- The height was reduced.
- This task was postponed.
- The smallest bolt size was M3.
Next meeting: 2016/8/1 13:00
Type-A Meeting on 2016/7/19
2016/7/19 13:00 - 15:00 @Room210
Participants: Takahashi, Ishizaki, Sato, Okutomi(Skype)
Minutes
- 0-1 Assy, (Ishizaki)
- The plate for BF is in the center of cross tube.
- Calculate the effect due to actuation point for BF.
- Remained horizontal deviation between the top flange on the cryostat and the top chamber was 1-4mm.
- The assembly work was rescheduled. From the end of August at the site.
- Additional 3 sets will be taken from NM1 in TAMA by the end of July.
- ACCs will be calibrated at the site.
- 3 sets were finished.
- Blades are in the thermal process.
- Samples of LVDT have been delivered from VIRGO.
- Design work is going.
- Made 3D model and some 2D drawings.
- Guide for lift down is necessary.
- Outer diameter of the plate will be reduced on 20th.
- Length of the present lead cable is too short. Longer ones will be prepared for actual setup.
- Rod for cryo-payload should be lift down at beginning and fixed on the protection net temporally.
- Made drawings. The present design is too tall.
- Confirm the height of mounted items.
- Check the small bolts size to decide the mesh of net.
Next meeting: 2016/7/26 13:00
Type-A Meeting on 2016/7/12
2016/7/12 11:00 - 12:30 @Kashiwa
Participants: Takahashi, Ishizaki(Skype), Sato, Okutomi
Minutes
- 0-2 Simulation (Okutomi)
- The frequency shift was due to damping model.
- Setting for GAS filters was corrected.
- Going BF damping simulation by manual tuning.
- Result will be reported by the VIS meeting.
- Horizontal position of the top flange on the cryostat was different from the center of the top chamber by 25mm along beam axis.
- The place should be in the center room of KAGRA considering DGS setup.
- 6 sets of ACC were measured.
- Additional 3 sets will be taken from NM1 in TAMA on 14th.
- Tube for the spot cooler was set.
- 2 sets were finished.
- Cutting of 22 blades was finished.
- Original design from VIRGO does not fit to the space around BF.
- The bending point is higher than the suspension point.
- Made outer shape of end plate.
- Assembling of the EQ stop prototype was started.
- Thin dummy weights were prepared.
- I-bolts on the plate were interfered with connection rods.
- Outer diameter of the stop plate was larger than inner diameter of the frame lock.
- 3 sensors were attached to the plate for the prototype test.
- Circular type weight is suitable for combined dummy load.
- Okutomi will send a cartoon soon.
- Protection for falling items is necessary. Check the small bolts size to decide the mesh of net.
- Discuss on evacuation of the chamber.
Next meeting: 2016/7/19 13:00
Type-A Meeting on 2016/7/5
2016/7/5 13:00 - 14:00 @Kamioka
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-2 Simulation (Okutomi)
- The frequency shift might be due to damping model.
- Matlab model was remade.
- Sensors and actuators were added to the BF stage.
- The booth will be ready in December.
- The schedule was shifted to December.
- From 8th July, presence on 11th.
- The place should be considered again.
- 5 sets of ACC were measured.
- Cutting of 12 blades was finished.
- Will be started in September.
- The first setup and its procedure were shown.
- Thin dummy weight and short hoock should be prepared.
- Some cap screws on stop plates should be replaced to stop screws.
- Under cable connection.
- Interferometer test was canceld.
- The EQ stop and the dummy payload should be ordered together in August.
- Situation of the Y-end was investigated.
- Maximum box width, which can go through the tunnel, was 1.5m.
- Access road from Mozumi entrance was improved.
- Ask CRY number of cables.
Next meeting: 2016/7/12 11:00
Type-A Meeting on 2016/6/28
2016/6/28 13:00 - 14:30 @The 4th meeting room
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assembly model (Ishizaki)
- Made the test setup.
- No progress. The results will be reported in the next VIS meeting.
- Present design: The booth is hung from the ceiling.
- From 8th July, presence on 11th.
- Working space: The 20m lab was arranged on 27th.
- Assembly of FR and measurement: 1 set was finished.
- Cutting: 6 blades by July + 6 blades by Sep.
- Device: It is difficult to put the devices at the center of suspension point.
- Modeling: 3D model for the test setup was built.
- Frame lock, extension rods, adjusters were delivered.
- Hoist's tool will be necessary.
- Test items related to the frame design have high priority. Target date is 22th July.
- Bases and shims were delivered.
- Plate additional machining: Delivery on 29th.
- Circuit: LED box was made. Cabling has not been applied yet.
- Cartoon: Okutomi should send to Ishizaki soon!
- Test plan is made parallel with test work. Check the list of test items.
- Situation of the site will be checked in 5-7th July.
- Electric crawler is limitted, for example, for 200kg load.
- Number of cables: CRY will decide it by the end of June.
Next meeting: 2016/7/5 13:00
Type-A Meeting on 2016/6/21
2016/6/21 13:00 - 14:00 by Skype
Participants: Takahashi, Ishizaki, Sato
Minutes
- 0-1 Assembly model (Ishizaki)
- Made the test setup.
- Deadline: The end of June
- Work: From 8th July, presence on 11th.
- Make working space in the 20m lab on 27th June.
- Assembly of FR and measurement: by August for 6 sets.
- Size: 13mm, 72PSC for each
- Cutting: 6 blades by July + 6 blades by Sep.
- Device: The last one was too small, actually about 125mm. Design for vertical as well.
- Modeling: 3D model for the test setup was build.
- Frame lock: Delivered by 24th.
- Other parts (rod, adjuster, bolts) will be ordered.
- Base: Making in ATC.
- Plate additional machining: Ordered.
- Circuit: LED will be tested.
- Cartoon: Okutomi should send to Ishizaki soon!
- Mirror holder: Refer the mirror box for PR.
- Test plan: Check FR for 2 BFs.
- Number of cables: Thermocouples are added. Ask Tomaru total number.
Next meeting: 2016/6/28 13:00
Type-A Meeting on 2016/6/14
2016/6/14 13:00 - 15:00 @ Room 210
Participants: Takahashi, Ishizaki, Sato, Okutomi
Minutes
- 0-1 Assembly model (Ishizaki)
- Step: From EQ stop, next with chamber.
- Problem: Conversion to Simulink was ok. The structure of control has a problem in Matlab. Reconstructing now.
- Space: Make working space in the 20m lab.
- Design: 5 blades are used for 200kg load.
- Device: Asking design of LVDT-Act. to VIRGO. The device is located at the center of mass.
- Structure analysis: Two cases were calculated. Share stress was 1/6 of limit, and principal stress was 1/7 of limit respectively in the maximum case.
- Modeling: Making with consideration of procedure and tools.
- Frame lock: Maximum stress was 160MPa with thickness of 30mm (limit 180MPa).
- Position: Inner side of the stage. Need to addtional machining to the EQ stop plate.
- Electronics: Circuit is simple in the test (handmade).
- Condition: 25cm mirror, alignment by moving mass. Make a cartoon.
- Actuation: Length control is necessary? Check PZT actuator.
- Test plan: Prepare for 2 sets of release sensors. Check FR for 2 BFs.
Next meeting: 2016/6/21 13:00