VIS Meeting on 2016/6/3
2016/6/3 13:30 -
Room 210
Participants:Takahashi, Sato, Ishizaki, Mark, Hirata, Fujii, Fabian, Aso, Shoda, Akutsu
Overall Schedule
The current overall schedule chart.
iKAGRA related activities
PR3
- PR3 post-run work status (Fujii)
- TF and Q measuremnts were done. Now analyzing the data.
bKAGRA preparation
Important Issues
- New meeting format (Aso)
- Each team will have individual meetings every week (F2F)
- Each team will report the progress at the plenary VIS meeting.
- Progress is checked against the schedule charts to be submitted by the team leaders by June 8th.
- The schedule chart should be updated whenever necessary
- After the progress check, important issues relevant to entire VIS team will be discussed
- The topics will be picked by Aso
- Everyone is welcome to suggest topics to Aso
- Will start the new format from the next week.
- Site check for the preparation of Type-A installation (Aso)
- Need check the transportation path of large items to the 2F of the end stations.
- Takahashi, Ishizaki, Sato will come to Kamioka in the week of July 4th contingent on Miyoki-san's availability
BS dummy mirror design (Mark)
- Larger reflector will be prepared by Akutsu-kun (will get quotes soon)
Accelerometers for IP
Is Geophone too noisy for innertial damping in Kamioka ? (Shoda) Slides
- If the noise of the Geophones is as described in the slides, using Geophone should be fine.
- However, the real noise of the Geophones is not well known. A measurement in Kamioka is necessary.
Shoda or Fujii will do the measurements along with the NIKHEF accelerometers sometime in June
- NIKHEF accelerometers for BS
- Test status (Fujii)
- Resonant freq. and Q of the accelerometer were shifted from the previous measurements (still a mystery)
- Did ring down measurements
- Necessary parameters to convert the output to m/rtHz are obtained.
- Still analyzing the data
Will present the results in the next VIS meeting
- Test status (Fujii)
- #Which accelerometers for SR ?
- # Buy from NIKHEF ? How much is the cost ?
- # Get the design from NIKHEF and produce them in Japan (ATC) ?
Pre-isolator assembly and tests
- Need to make a plan for the assembly of the SRC PI.
- If possible assembly by Sato-san is better as he will do it for Type-A too.
- Takahashi will make more detailed schedule for PI assemblyto see if Sato-san can do the SRC work.
Dummy payload design for Type-A
- SEO is now considering if we can use the iKAGRA ETMs for this or not.
Bottom Filter LVDT -> To be discussed at the next meeting
- Virgo people wants to produce ones for us.
- Status ? (Raffaele)
- #Assembly frames
- We need to combine things into one contract
Type-B assembly frame: order immediately (Takahashi)
Common Issues
- Wide OSEM production (Akutsu)
Flexible circuit status ?-> asked for quotation to the company (6/2).
Electronics
- List of requested electronics from VIS
Need to add satellite boxes for IMMT (2 of them) to the list (Takahashi)
- IMMT OSEM cables will be different from other OSEMs
- #Watch dog system (Tanaka)
- photo-MOS relay switch resistance fluctuation
- Noise requirement for the resistance fluctuation is necessary (Aso)
- If we require the resistance noise to be smaller than DAC noise, the allowed fluctuation is 10^-7 Ohm/sqrt(Hz)@10Hz.
- Asking Michimua-kun to calculate the requirements from the suspension response.
Tanaka measured the photo-MOS relay resistance fluctuation-> 37mOhm RMS upper limit
- Will make spectrum of the resistance fluctuation.
- Noise requirement for the resistance fluctuation is necessary (Aso)
- photo-MOS relay switch resistance fluctuation
Type-B
- Type B Past Week Summary
Fabian worked on IM and dummy BS assembly: photos1, photos2
- A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece.
- Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them.
- Some arrows were cleaned from the mirrors for the dummy optic.
- Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found.
- Hirata-san measured another filter.
- Hirata-san washed a large batch of parts.
- All parts for gluing of dummy BS are in hand. We arranged with Tatsumi-san to glue magnets at Mitaka on 6/6, glue flags at Kashiwa on 6/8, and inspect bonds and bring dummy BS back to Mitaka 6/13.
Mark worked on solutions to allow a larger mirror on dummy BS. After discussions with Simon and Akutsu-san we decided to go with a stainless steel plate solution. The gluing can go ahead and we can attach the plates later.
- Mark worked on list of items for purchase in FY2016.
- Mark worked on finding connectors for vacuum-compatible geophone adapters.
Mark worked more on E1504235 BS Assembly Procedure (Draft on OneDrive)
Discussions
- BS assembly frame contract: ordered. delivery date = July 8.
Review: send doodle poll (Mark)
Type A
Task list (Takahashi) -> working on more detailed one.
Clean booth design for 2F https://www.dropbox.com/s/8bi9ij91radmpt5/IXYV160512.pdf?dl=0
- Discussing with Miyoki-san (Takahashi, Aso)
- Prototype test of the EQ stop
- Cleaned the ATC room for starting the test
- Frame lock: made a design change to make it stronger. Will order it next week.
- Sensors to monitor the release of the SFs from the EQ stop.
Updated Design
- Type-B Standard Filters preparation
- Will start the measurement of the SFs for Type-A from the next week.
- The next Type-A meeting will be on 6/9.
- #Simultion (Okutomi)
- #Local sensors for BF
Type-Bp modification
Modification for bKAGRA
Saito-san of ATC produced the first draft design -> now checking the design (Shoda)
First draft of the installation procedure & Checking if there is any conflict (Fujii)
- Still waiting for the LVDT design from Virgo
- Full CAD model of the original Type-Bp is almost done (Shoda)
- A/I till next week
- First draft of the installation procedure (Fujii)
- Full CAD model of the original Type-Bp and the new Type-Bp (Shoda)
Site work plan for the next week
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
BS crane will not be available: 13th -14th of June
Travel Plans
- Travel (Week of 6/6)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
- Sato:
- Travel (Week of 6/13):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
Mark is away: July 8-20
Other
- Safety: no incident
- #GAS blade inspection by Virgo (Takahashi)
- Shipped the blades. Will get results in 1-2 months.
Next meeting
2016/6/10(Fri) 13:30 -
Next VIS F2F 6/17
Next next F2F 7/8