Minutes of the VIS Meeting on 2016/6/17

2016/6/17 13:30 - 15:00 @ Room 210

Participants:Fabian, Hirata, Takahashi, Sato, Shoda, Ishizaki, Mark, Aso, Raffaele, Akutsu

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

Type-B (Mark)

Type-Bp (Shoda)

IMMT (Ohishi)

Watchdog system (Tanaka)

Safety

Issues

Site work plan for the next week

BS crane will not be available: 13th -14th of June

Travel Plans

July 5 - 7: Takahashi, Ishizaki, Sato (site check for the installation of Type-A)

Mark is away: July 8-20

Next meeting

2016/6/24(Fri) 13:30 -

Next F2F 7/8