Agenda/Minutes of the VIS Meeting on 2017/7/21
2017/7/21 13:30 - 15:50
Participants: Mark, Enzo, Ishizaki, Fabian, Shoda, Aso, Okutomi, Tanaka, Simon, Sato, Takahashi, Ohishi, Raffaele
Progress report
- Type-A: On schedule
- Type-B: 1.5 weeks delay, but by re-arranging the works, there will be no net delay in the overall schedule.
- Type-Bp: 1 week ahead of schedule
Type-A (Takahashi)
Past week report
[X-end]
19th(Wed)
- Transported some items from Y-end to X-end.
20th(Thu)
- Preassembled the BF damper.
- Measured the weight of DP and BF.
- Replaced the receptacles in the BF.
- Replaced the blades for FR in the BF.
- Replaced the cable clamps on the BF
- Set the release sensors for the BF.
21st(Fri)
- Adjusted the rotation of frame lock.
- Hooked the short maraging wire to the BF. The DP was suspended from the BF.
- Tuned the BF roughly. The optimal frequency was about 0.5Hz. More compression is necessary.
[Y-end]
18th(Tue)
- Cabled from the cryo-payload to the BF.
- Closed the EYV chamber completely, The o-ring was replaced.
19th(Wed)
- Checked the cable connection. One cable was disconnected.
- Unplugged in-air cables from feedthroughs.
- Closed the cross tube completely.
20h(Thu)
- The brackets for the corrugate tube were replaced. Measured the height of the EYV chamber.
21st(Fri)
- Plugged in-air cables to feedthroughs.
- Started evacuation of the chamber.
Plan for coming weeks
- Monitering behavior of the Type-A tower in Y-end.
- Installation of the bottom filter in X-end.
Type B (Mark)
Past week report
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
- We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
- Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
- We craned the PI. There was a minor safety incident - see below.
- Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
- Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
- We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
- We set up the BS gluing jigs and applied the glue. We will check the results on Monday.
Plan for week of 7/24
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
- Check results of gluing.
- Finish disassembly.
- Finish BF rebuild.
- Recheck alignment of assembly frame and centering of optical table.
- Install IM, suspend BS and RM.
Plan for week of 7/31
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
- Remove LBB rings.
- Weigh/trim BS/RM/IM.
- Bring in rebuilt BF.
Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct
Type-Bp (Shoda)
Past week report
- IM TF measurement
- IM TFs seem to be OK.
- The coupling from IML to TMP could not be observed with Oplev with a good coherence. The coupling ration should be less than 10^-1 rad/m with a rough estimation. (Some parameters need to be checked.)
- All parts are assembled on the suspension.
- BF/BFRM parts are assembled except that BF/IM/TM are not suspended from the SF.
- Cabling is almost done.
- Berndy male pins are running out.
Plan for coming weeks
- Suspend the BF and blow from the SF, and adjust the weight and the balance
- TF check
- Installation preparation
- Prepare for PRM Traverser shipping.
IMMT (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
Order electronic parts -->No delivery(Coop Univ.Tokyo).
Order PCB's(Ex-I/O Interface and relative PCB's) -->Delivery complete.
- Looking for board manufacturer(Manufacturer who makes PCB manufacturing and mounting(including parts procurement).
- Start of preliminary experiment at KAGRA site.
Start production of equipment(As soon as parts are delivered).-->Start PCB check.
Plan for coming weeks
Experiment schedule(for KAGRA site).-->24th( Tokyo-->Toyama ),25-26th full(KAGRA),27th(Reserve and Toyama --> Tokyo )
Other site works
- 7/25 - 26: Y-arm water pump exchange
- End of Aug. to Nov.: Mozumi entrance will be closed
Safety
- Incidents:
- One of the rods supporting the SF damper ring of the BS came off while pulling the suspension out of the chamber.
- Dropped a tool from the second floor to the first floor while working on PR2
- When taking out the clamps for the clean booth floor panels, bottom part of the bracket fell to the first floor.
- Foreseen risks
- Type-A: Crane work BF EQ
- Type-B: Crane work SF, BF
- Type-Bp: No crane work
Discussion
- What to do with the dirty maraging rods supporting the SF damping plate.
- Check the number of rods and the receptacles we have now (Mark, Fabian, Takahashi)
- Order new rods if the number is not enough
- Send the current rods for nickel plating (Takahashi)
- Check the number of rods and the receptacles we have now (Mark, Fabian, Takahashi)
- Signal generators for LVDT
- Takahashi-san will send VIS the information of the NIKHEF daughter board
- Share the information with AEL and discuss whether we should buy those boards or do something else
Travel Plans
- Travel (Week of 7/24):
- Takahashi: 24 - 28
- Okutomi: 24 - 28
- Sato: 24 - 27
- Ishizaki: 24 - 28
- Mark: 24 - 28
- Fabian: 24 - 27
- Hirata: 25 - 28
- Enzo:
- Shoda: 24 - 27
- Ohishi:
- Fujii:
- Tanaka: 25 - 26 (27)
- Kuroki: 25 - 28
- Hashimoto(Hosei): 24 - 27
- Yoshioka (Toyama): 25,26,28
- Travel (Week of 7/31):
- Takahashi:
- Okutomi: 31 - 4
- Sato: 31 - 4
- Ishizaki: 31 - 4
- Mark: 31 - 4
- Fabian: 31 - 2
- Hirata: 31 - 4
- Enzo:
- Shoda: 31 - 4
- Ohishi:
- Fujii:
- Tanaka:
- Kuroki: 31 - 3
- Hashimoto(Hosei): 31 - 3
- Yoshioka (Toyama): 1,2,4
- Kouzu: 3,4
Next meeting
On 2017/7/28(Fri)