Agenda/Minutes of the VIS Meeting on 2018/1/26
2018/1/26 13:30 - 14:20
Participants: Mark, Okutomi, Sato, Fabian, Aso, Takahashi, Ishizaki, Simon, Hirata, Enzo, Tanaka
Progress report
Schedule Chart
Type-A : (PDF/MPP)
- Type-A:
- Type-B:
Type-A (Takahashi)
Past week report
[X-front]
- Assembled the DP. Measured the weight of DP.
- Mounted the DP onto the end plate.
- Extended the EQ stop to the BF stage.
- Assembled the release sensors for BF.
- Replaced the receptacles in BF.
- Assembled the blades for FR in BF.
- Cabled to the connectors for LVDT, actuator, picomotor, stepper motor, and PT100 in BF.
- Assembling the primary and secondaly coils for BF damper.
- Repairing the side stoppers.
- Opened the box for TFs and checked the blades. There were not broken blades.
- The broken blades were already sent to Virgo for inspection.
- Inspected the delivered items (ballast rings and D-sub connectors).
[Y-end]
- Started the evacuation of EYV chamber on 24th. The IP was moved by 0.3mm to T-direction.
[X-end]
- Checked flanges using alcohol. Leak points were not found. The present pressure is 8Pa.
Plan for coming weeks
- Open the top chamber and the cross tube.
- Start the tuning of BF.
Type B (Mark)
Report for week of 1/15
- We swapped in the other available BF, and it was rather better: only 0.3 mm of keystone tilt rather than 1.3 mm. We will use it for the SR2 and then think about whether we want to use or rebuild the original one.
- There are 4 spare blades for SR BF. Since we need to re-assemble at least one for SRM, we should re-assemble the tilted one too.
- We finished the preparation of the second BF, setting the yoke, adding the new-style cable clamps etc.
- We changed the 1.6 mm sockets on the BF LVDT cable to 1.0 mm ones to match the pins on the LVDT wires. The specification of the cable in D1503901 was apparently wrong. We will update it (today) before doing the cable order for the SR3 and SRM.
- We updated the BS real-time model and screens, adding support for a damping filter common to both the OL-TM and OL-IM paths, per Izumi-san's suggestion in G1807653.
- We set up the router for the SR2 rack and got the SR2_IM pico driver and both stepper motors on the network (the SR2_BF pico is still on order).
- We did prep for the top filter test:
- Hirata-san sent off a shipment of weights and other parts from Mitaka.
- We received the shipment at Kamioka and unpacked and temporarily stored it.
- We cleaned up the SR3 assembly frame and removed the top crossbars.
- Hirata-san ordered another two suspensions' worth of cable clamp parts.
- Hirata-san arranged with ATC to start the widening of the slots in the remaining RMs.
Plan for week of 1/29
- Enzo at Mitaka 1/29 and most of 1/30, then vacation.
- Kozu-kun away.
- All others at Kamioka.
- Make in-air pico adapter cables.
- Test IM picos and BF yaw pico.
- Test FR.
- Calibrate LVDT.
- Get screws for ballast mass from Takahashi-san.
- Install ballast mass in BF.
- Set up for F0 test.
- Lower IM crossbars in SR3 assembly frame.
- Open curtain on SR3 crane slot.
- Set up dummy load (weight carrier, rods etc).
- Do F0 test.
- Bring in F0.
- Hook up dummy load.
- Adjust dummy load.
Plan for week of 2/5
- Enzo on vacation; all others at Kamioka.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Plan for week of 2/12
- Enzo on vacation; all others at Kamioka.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Start ordering sequentially for mass products. --> Completed. And order processing end.
Preparation for assembly of mass products.--> Ongoing.
Plan for coming weeks
- Preparation for assembly of mass products.
- Adjustment and approval to vendors(Meeting on machine design etc).
Other site works
- Feb 18: Black out of the Mozumi buildings
Safety
- Incidents: no
- Foreseen risks
- Type-A: Crane works
- Type-B: Major crane works
- Type-Bp:
Discussion
- bKAGRA phase 2 roadmap
- We want to install SRM as early as possible so that the dummy DRMI test can be performed with SRM.
- We need detailed Gantt charts for all the Type-A and Type-B installation works by the end of the next week (Mark and Takahashi)
- We also need to prepare two kinds of check lists
- Acceptance checklist: Things to be tested/confirmed before we declare the finish of installation.
- Request checklist: For each milestone (e.g. starting mechanical assembly of ITMY), we need to prepare a checklist for requesting other subsystems. For example, "A digital system needs to be ready for SR3 by XXX".
- Suspension realtime model update proposal from Izumi-kun
- We agree to the proposed changes
Travel Plans
- Travel (Week of 1/29):
- Takahashi: 30 - 2
- Okutomi: 29 - 2
- Sato: 30 - 2
- Ishizaki: 30 - 2
- Mark: 29 - 2
- Fabian: 29 - 2
- Hirata: 30 - 2
- Enzo:
- Shoda: 29 - 2
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 2/5):
- Takahashi: 7 - 9
- Okutomi: 5 - 9
- Sato: ? - 9
- Ishizaki: ? - 9
- Mark: 5 - 9
- Fabian: 5 - 9
- Hirata: 5 - 9
- Enzo:
- Shoda: 5 - 9
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR): 5 - 9
- Arai (ICRR):
Next meeting
On 2018/2/2(Fri)