Agenda/Minutes of the VIS Meeting on 2018/8/3

2018/8/3 13:30 -

Zoom Meeting

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

[IYV]

1.Assembling Pre-isolator

We prepared for pre-isolator installation. - Magnetic damper ring was placed on F1. - EQ-Stop structure was extended to the top ring. - We installed bridge frame on the scaffoldings. - We combined IP and TF.

We replaced the top filter blades. - In order to replace the blades,we removed all blades from TF. - We bent 6 new blades and attached it to the Top Filter.

We attached the following equipment to the PI. - Connectors, Auxiliary blade (for F1 FR), Fishing Rod for TF. But FR was not completed due to lack of parts.

2.Installing Pre-isolator

- We put the pre-isolator on the bridge frame and hanged F1 or less.

Result of hanging F1 or less

TF was able to lift F1 or less.

3.Calibration of the LVDTs for BF damper.

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

VIS electronics (Tanaka)

Past week report

Plan for coming weeks

Other site works

Safety

Discussion

Travel Plans

Next meeting

On 2018/8/10(Fri)