VIS reports for the week ending on 2018/10/26
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-C: (XLSX)
Type-A (Takahashi)
Past week report
[Y-front]
- Removed the secondary coils for BF damper. Opened the cup.
- Removed the old parts to fix the FR blades, then the upper blade was broken (cut off).
- Removed the FR blades.
- Attached the new parts onto the keystone with the new blades.
- Tuned the BF.
- Checked the range of FR. I was 69 +/- 3 mm in the height of keystone.
- Closed the cup. The optimal load was changed. Finally the additional weight for DP was 1.2kg.
- Attached the secondary coils for BF damper.
- Adjusted the weight on the BF.
- Adjusted the position of secondary coils.
Plan for coming weeks
- Preparation of the wire for cryo-payload in IYC.
- Measurement of dimensions around the IP in EYV.
- Help in OMMT.
Type B (Mark)
Report for week of 10/22
SRM
- We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
- Fabian adjusted the last two OSEMs (IM-H2 and H3).
- We closed the BF and weighed the BF/... section.
- Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
- We built up the assembly frame and security structure to the SF level and craned in the SF.
- We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.
- Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
- We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
- Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.
SR2
- Akutsu-san gathered the parts we will need for the SR2 OL so that Terrence can install it next week.
- Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.
Plan for week of 10/29
- Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
SR2
- Set up OL.
- Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
- Possibly add more arc weights, to get below 0.1 Hz.
SRM
- Electronics
- More cable soldering?
- Get soldered cables ultrasonically cleaned.
- Collect unused cables for return to AEL.
- PI
- Finalize tuning.
- Add more cable clamps.
- Prepare SF magnet ring.
- Main sequence
- Cable/test SF LVDT and FR.
- Decide and install SF internal ballast mass (probably 1 Promec).
- Reinstall SF cap.
- Weigh SF/... section.
- Install #353 poles
- Move NB-03 jacks down.
- Crane PI into AF.
- Install F0-SF rod (#331) and flying saucer.
- Route SF/... cables up to underside of F0.
- Do vertical height budget.
- Adjust SF trim mass for balance and keystone height.
To-Do Lists, Schedule
Plan for week of 10/29
- Mark, Enzo, and Fabian at Kamioka Mon-Fri.
- Hirata-san at Kamioka Mon-Thu (compensation day).
SRM
- Main sequence
- Cable/test IP LVDTs.
- Cable/test IP FRs.
- Unlock IP and center roughly.
- Calibrate IP LVDTs.
- Check/adjust alignment of SS.
- Add arc weights and geophones (or extra mass equivalent to geophones).
- Cable/test geophones.
- Improve centering/tuning of IP and SS alignment.
- LBB
- Move KOACH filters
- Put LBB damper rings in tank.
- Set tank jacks to nominal height.
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
Discussion
Travel Plans
- Travel (Week of 10/29):
- Takahashi: 10/30-11/2
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 11/5):
- Takahashi:
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2018/11/2(Fri)