Agenda/Minutes of the VIS Meeting on 2019/1/11
2019/1/11 13:30 - 14:50
Participants: Takahashi, Mark, Ishizaki, Sato, Fabian, Aso, Okutomi, Terrence, Enzo, Ohishi, Hirata, Fujii, Lucia
Progress report
Schedule Chart
Schedule for the site work meeting: Weekly schedule 190115-VIS.xlsx
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-C: (XLSX)
Type-A (Takahashi)
Past week report
[Y-end]
- Calibrated the LVDTs for BF damper.
- Started the evacuation of EYV chamber. The IP is touching the stopper.
[X-end]
- Prepared for the payload extraction. Fixed the BF and pushed down the keystone of TF.
- Replaced the yaw FR.
[X-arm measurement]
- Measurement campaign with X-arm was conducted.
- Some stages were excited and then the couplings to the TML etc were measured.
- Excited dofs were: TML / IML / MNL / IPL / (partly BFL) / BF-GAS / IMV / TMP
- The purpose was to get the followings:
- Vibration isolation performance (GND2TML)
- force transfer functions of TML2TML, IML2TML, MNL2TML
- couplings of V2L, P2L (somehow I forgot to measure Y2L coupling)
- Now analysis is ongoing.
force TFs are in klog#7573
Plan for coming weeks
- Replacement of the yaw FR in X-front on 17-18.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
Discussion
Confirmation of the VIS schedule for Jan.
Thesis defence practice
- Kozu-kun and Arai-kun: after the next VIS meeting (12/21)
Travel Plans
- Travel (Week of 1/14):
- Takahashi: 15-18
- Okutomi:
- Sato: 15-18
- Lucia: 15-18
- Fabian: 15-18
- Mark: 15-18
- Hirata: 15-18
Enzo:15-18
- Shoda:
- Ohishi:
- Fujii: 16-18
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 1/21):
- Takahashi: ??
- Okutomi:
- Sato: ??
- Lucia: 21-25
- Fabian: 21-25
- Mark:
- Hirata: 21-25
- Enzo: 21-25
- Shoda:
- Ohishi:
- Fujii: 21-25
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2019/1/18(Fri)