Agenda/Minutes of the VIS Meeting on 2019/1/25

2019/1/25 13:30 - 14:45

Zoom Meeting

Participants: Takahashi, Sato, Mark, Tanaka, Ohishi, Aso, Lucia, Fabian, Fujii, Enzo, Ishizaki

Progress report

Schedule Chart

Site work schedule: XLSX

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-C: (XLSX)

Type-A (Takahashi)

Past week report

[Y-front]

[X-front]

[Y-end]

Plan for coming weeks

Type B (Mark)

Past week report

BS (top priority)

SR2 (priority 2)

SR3 (priority 2)

Talk about problems turning on and off control systems (Terrence and Enzo) From Terrence: Since the PI controller was implemented, the controller keeps accumulator displacements error and converts this error to the output. One problem arose from the mismatch of the control system and the actual hardware. Because the controller output could have a much larger value than the number of counts that can be input to the coil actuators (e.g. the controller says we should input 60000 counts to the actuators but the hardware limits the number of counts), the controller will not function as designed. As a result, the PI would shift to one side (due to insufficient driving force) while the voices coils became saturated at maximum output. Additionally, because the controller is still functioning, the integrator keeps accumulating error and hence the output of the controller keeps increasing but the object is actually stuck. This makes the IP very very unstable when the actuators are saturated.

SRM (low priority)

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

VIS electronics (Tanaka)

Past week report

Plan for coming weeks

Other site works

Safety

Discussion

Updated KAGRA schedule

SR2 and SR3 must be ready: 1/26

SRM must be ready: 2/4

Vacuum monitoring

Travel Plans

Next meeting

On 2019/2/1(Fri)

KAGRA/Subgroups/VIS/VISMinutes20190125 (last edited 2019-01-28 14:48:58 by MarkBarton)