Agenda/Minutes of the VIS Meeting on 2019/3/29
2019/3/29 13:30 - 14:30
Participants: Hirata, Sato, Ishizaki, Mark, Aso, Lucia, Fabian, Tanaka, Takahashi, Fujii
Progress report
Schedule Chart
Site work schedule: [[|XLSX]]
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-C: (XLSX)
Type-A (Takahashi)
Past week report
[Y-end]
- Checked the connectors on the BF. Cable trouble was recovered without doing anything. The cable has been damaged ever in the installation work (2017).
- Swapped the channel assignment in the cable with trouble just in case.
- The F0 is not working. Confirmed that the LVDT is working but the actuator is not.
Plan for coming weeks
Type B (Mark)
Report for the week of 3/25
- Fabian and Terrence monitored the suspensions during the vent.
- Mark and Fabian helped Fujii-kun with PR2. The problem turned out to be two broken flags. Hirata-san drew up a design for a jig to help reglue the flags in situ.
- Mark asked LIGO colleagues about use-by dates for EP30-2. Masterbond says it's good for 6 months in cartridge form and 12 months in jar form (although presumably only if the jars are not opened). If it's too old it may remain tacky after curing. The batch that Type B has was manufactured 2017-11-02 and KEK has a batch from early 2018.
- Fabian scraped glue off the broken flags, and Mark delivered them to Hirata-san for acetone soaking and further cleanup.
Fabian documented the height budget for the Type B suspension in the wiki (KAGRA/Subgroups/VIS/OpsManual/TypeB/SR3Data etc).
- Terrence wrote up the final version of his OL diagonalization scheme.
- Terrence worked on L2P decoupling for the TM.
- Terrence and Mark edited the Type B Guardian to turn on the payload damping later in the sequence, after IP and GAS, to help ensure that the OSEMs are not touching by the time they're needed (which can happen if the BF is buoyancy compensated for vacuum but the suspension is vented).
- Mark started on a big tidy-up of the cleanbooth.
Plan for week of 4/1
- Mark, Fabian at Kamioka Mon-Fri.
- Assist with PR2.
- Work on Type B paper.
- Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
- Tidy up.
- Gather and clean tools.
- Gather and organize unused parts and fasteners.
- Return all unused cables to tent.
- Tidy up cables in rear of SR2 rack.
Vacation/Travel Info
- Enzo's last day 3/29.
- Terrence's last day for now, 3/29.
- Mark compensation day for 3/21: 3/29. (He is not really typing these minutes, and anyone who sounds like him in the meeting is an impostor!)
- Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
- Terrence's next visit from 4/18.
- Fabian's vacation 4/26 to 5/10.
- Mark's vacation from about 5/22 to 6/11 (TBD).
- Mark's final day 6/28.
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
- LVDT signal generator board delivered to Kamioka
Plan for coming weeks
Other site works
Safety
- Incidents: no incident
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp: Vacuum flange work
Discussion
- Vacuum monitoring
- ETMY: April 3rd (Wed): Lucia, Fabian
- ITMX: April 4th (Thu): Lucia, Fabian
- Center area: April 12th (Fri): Fabian, Mark
- Suspension health check before pumping
- Type-B: Mark, Fabian
- Type-Bp: Okutomi, Shoda ?
Travel Plans
- Travel (Week of 4/1):
- Takahashi: 4-5
- Sato:
- Mark: 1-5
- Hirata:
- Shoda:
- Ohishi:
- Fujii: 2 - 4
- Tanioka:
- Tanaka:
- Terrence:
- Travel (Week of 4/8):
- Takahashi:
- Sato:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii: 9-12
- Tanioka:
- Terrence
Next meeting
On 2019/4/5(Fri)