Agenda/Minutes of the VIS Meeting on 2020/7/17
2020/7/17 14:00 -
Participants:
Progress report
General
Type-A
- Preparing for the site test of the modified ACC.
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- KAGRA new state "Upgrade phase for O4 (bKAGRA phase 4 ??)" started from 11th July.
- Control update of SRs are on going.
Schedule towards O4 (Chart) was revised.
- Some related tasks on FCI/VAC/CRY/DGS were added.
- Preparation work (pre-cleaning) is avairable from 17th Sep.
- Opening chambers will be started from 19th Oct.
- Disassembly of ETMY will be started from 7th Dec.
cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List).
Safety
Discussion
- Plan for cleaning the clean booth.
Travel Plans
- Takahashi: 7/20-22
Next meeting
- On 2020/7/31(Fri)