Agenda/Minutes of the VIS Meeting on 2020/9/11
2020/9/11 14:00 -
Participants:
Progress report
General
- The VIS-CRY integration meeting will be set at 13:30-14:00 weekly just before the VIS meeting.
Type-A
Type-B
Type B
Report for the week of the 7th of September 2020.
- I finished the corrections of the Type-B paper. Mark is checking the final vesion and I will submit as soon as he is finished.
Miyo-kun, Ikeda-san and I went to the mine and did ballast mass inventory (14998):
- Fabian is in the process of checking roghly how much we will need.
- We checked for rectangular ones for the top of IM, round ones for the top of BF and arch weights for IPs.
Pictures and the actual inventory are in a new album in Google Photos: SR3 Remedying work after O3.
Pictures of the top of SR3 IM: IM_top_1, IM_top_2, IM_top_3, IM_top_4, IM_top_5, IM_top_6. We will likely need to replace thick ones by thinner ones with the same weight and then remove from opposite corners.
In the procedure document I wrote that we must measure the bouyancy displacement effect when we to the venting. Importanrt for the adjustment of the ballast masses in BS and SR3.
- Before we did the pumping down with the contro on, so we only know the change in feedback signal. (I should use TF vales to calcilaye displacement.)
- We should do it with the control off just to measure the displacement directly.
For SR3 and SRM I measured the resonant frequencies of IPs (klog 15013).
- SRM IP looks fine.
SR3 IP requires adjustment, the resonant frequencies are relatively high and there's a large assymetry between L and T. We have very small arch weights to fix the assymetry. What's the TAMS300 experience?
I tried to assess the consequence of having ferromagnetic connectors close to magnets on top of SF (klog 15011): inconclusive results.
- I haven't checked Sato-san's cable alternative proposal.
Type-Bp
Type-C
Controls
Electronics
Towards O4
- KAGRA is in "RSE Trial" now.
- Procedure documents.
- Preparation work.
- The preparation work will be started on Oct. 1st.
Acceptance Test (Wiki page).
- Schedule towards O4.
(Two cases).
cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List)
Safety
Discussion
Travel Plans
Next meeting
- On 2020/9/18(Fri)