Contents
Activities in this week
VIS/OMM, 15617, ryutaro.takahashi: Modification of ACCs
VIS/OMM, 15872, ryutaro.takahashi: Comment
VIS/SR2, 15684, satoru.ikeda: Support for common Payload model files: Payload of Type-B (SR2) is supported to PAYLOAD_MASTER.
VIS/SR2, 15937, kouseki.miyo: Comment
VIS/General, 15737, satoru.ikeda: We investigated the network connection.
VIS/General, 15877, satoru.ikeda: Comment
VIS/PR3, 15844, fabian.arellano: Gluing the mirror wire.
VIS/General, 15847, satoru.ikeda: Relay Switch of Stepper Motor Driver
VIS/General, 15873, kouseki.miyo: Comment
VIS/PR2, 15857, satoru.ikeda: The PR2-SF's stepper motor has stalled.
VIS/General, 15868, kouseki.miyo: Some suspensions are not SAFE.
VIS/General, 15923, kouseki.miyo: Comment
VIS/PR3, 15889, fabian.arellano: Traverser motor test and cabling.
VIS/EY, 15891, ryutaro.takahashi: Setup of F3
VIS/EY, 15919, ryutaro.takahashi: Setup of BF
VIS/SR3, 15928, fabian.arellano: Oplev installation and alignment recovery.
VIS/SR3, 15935, kouseki.miyo: Comment
VIS/EY, 15932, ryutaro.takahashi: Setup of F3
VIS/EY, 15936, kouseki.miyo: Comment
VIS/PR3, 15886, satoru.ikeda: Driveable range of the PR3 GAS SF stepper motor
VIS/General, 15888, kouseki.miyo: All payload models are in PAYLOAD_MASTER.mdl
VIS/PR3, 15889, fabian.arellano: Traverser motor test and cabling.
VIS/EY, 15891, ryutaro.takahashi: Setup of F3
VIS/EY, 15910, kouseki.miyo: TF measurement for F3 GAS filter
VIS/EY, 15919, ryutaro.takahashi: Setup of BF
VIS/SR3, 15921, fabian.arellano: Oplev installation.
VIS/SR3, 15928, fabian.arellano: Oplev installation and alignment recovery.
VIS/PR2, 15930, satoru.ikeda: Connect and check the drive of the PR2 traverser.
VIS/EY, 15932, ryutaro.takahashi: Setup of F3
VIS/General, 15938, kouseki.miyo: Comment to Support for common model files: Installation on Type-A (ETMX, ETMY, ITMX) and Type-B (SRM, SR2) (Click here to view original report: 15641)
VIS/EY, 15950, ryutaro.takahashi: Setup of F2
Agenda/Minutes on 2021/2/5
CRY+VIS Interface Meeting
13:30-14:00
Participants:
VIS Meeting
14:00-14:40
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 2/8
- Takahashi: 2/8-12
- Sato: 2/8-12
- Hirata: 2/8-12
- Yano: 2/8-12
The week from 2/15
- Takahashi: 2/15-19
- Sato: 2/15-19
- Hirata: 2/15-19
- Yano: 2/15-19
Next meeting
- On 2020/2/12(Fri)