Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/8/27 12:30-
Participants: Takahashi, Tomaru, Ikeda, Aso, Hirata, Sato, Ushiba
Schedule
- IX: In finalization.
 - EX: In finalization. Installation of ACCs will be scheduled in the next-next week.
 - IY: Height measurement/adjustment was scheduled on 9/1.
 - EY: Repair of cables was scheduled on 8/31. Load adjustment was scheduled on 9/2. Chamber closing is scheduled on 9/6-8.
 
Status
- TM height setting: ITMY.
 - Commissioning in air: On going in X-arm.
 - Commissioning in vacuum:
 - Overall commissioning:
 - Acceptance check: Every Friday.
 - PF actuator: At the in-vacuum commissioning.
 - New vacuum pumps for V-chambers:
 
Discussion
VIS Meeting
Cancel
Participants:
Klog
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team:
 - Type-B team:
 
Milestone
IMC suspensions are ready in air [40] will finish 2021/04/21.
PRs are ready in air [643] will finish 2021/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2021/11/24.
SRs are ready in air [663] will finish 2021/12/20.
Output suspensions are ready in air [695] will finish 2021/12/21.
TMSY is ready in air [708] will finish 2021/??/??.
TMSX is ready in air [684] will finish 2021/??/??.
2021/03/29 updated
Safety
Discussion
Travel Plans
The week from 8/30
- Takahashi: 8/31-9/3
 - Sato: 8/30-9/3
 - Hirata: 8/30-9/3
 
The week from 9/6
Next meeting
- 2021/9/3(FRI)
 
