Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2023/2/17 13:00-13:10
Participants: Takahashi, Mitsuhashi, Ikeda, Sato, Kimura, Miyoki, Aso, Yasui, Hirata, Yokozawa, Ushiba
Status
- Type-A: Investigation of ACCs in EY.
- Type-B:
- Type-Bp: Sensor correction in PR3.
- Type-C:
Other items
- Oplev:
- ACC: Replacement of the coil driver in EY was postponed.
- Commissioning:
- Vacuum system: Switched from the TMP to the ISP in SRM.
- Heater control:
- TMS: Covering in TMSY on 2-3 March.
Discussion
VIS Meeting
Date: 2023/2/17 13:30-13:55
Participants: Takahashi, Ushiba, Mitsuhashi, Fabian, Tanaka, Aso, Akutsu
Summary Report
Type-A
Replacement of the coil driver for ACCs in EY was postponed. A strange peak in the signal of ACC only is observed at 0.02Hz (klog).
Type-B
Type-Bp
- PR3: I calculated the inter-calibration factor between the seismometer on ground and the BF Damper in L.
- PR2: I tried to do the same for PR2, but the data is very noisy, and I was not able to get a reliable transfer function fit. It would be useful to get data with higher coherence.
Type-C
Electronics
Tested a prototype pre-amp board for geophones using the spare geophone pod and the geophone distributor. The prototype board had the noise floor higher than the Nikhef one by one order at 1Hz (klog).
Control
Schedule
- Type-A: IP control with ACCs.
- Type-B/Bp: Sensor correction for PR3 and PR2.
- Type-C:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 2/20
- Takahashi: 2/20-22
- Hirata: 2/22
The week from 2/27
- Aso: 2/27-28
Next meeting
- 2023/2/24(FRI) 13:30-