Differences between revisions 1 and 74 (spanning 73 versions)
Revision 1 as of 2017-10-03 12:10:54
Size: 167
Comment:
Revision 74 as of 2017-10-19 09:23:57
Size: 5077
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
-----
== Working people assignment ==
 * MIF + VIS
  
  * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  .
  * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
Line 3: Line 16:
 * [[KAGRA/Commissioning/Meeting|Meeting]]  . * 責任者
-----
-----
== Meetings ==
Line 5: Line 21:
----
=== Morning meeting ===

 * Date and time: Every weekday, 9AM
 * Location: Control room, or educe


2017/10/17(Tue)

 * Daily
  * 作業人員(*:責任者)
   * MIF+VIS: *和泉、榎本、中野、神津、新井、正田、井上、灰野、横澤、宮川 (PHS: V-3(榎本), V-7(中野), V-12(横澤))

Fabian、Enzo、平田、

  * Laser hazard
   * PSL直後で100mW、IMC出口で50mW程度、PRM以降は5mW程度。
   * 今日のある時点からハザードエリアがSR2とSR3の間のラインより奥(機械室は除く)になる。
   * 中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。
   * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを各自1個ずつ持っていって下さい。そして、もし、中央エリアがハザードエリアになった場合は、帰りなどに中央エリアを通る際は保護メガネの着用をお願いします。保護メガネは、前室の入り口横に移動される保護メガネ台に返してください。
   * Xエンドに行く方は保護メガネは必要ありません。

  * 作業
   * アラインメント(中野)
    * BSまで光が到達した。X方向に打ち込んでいる。ゲートバルブのビューポートの端に通っている。
    * PR3のお辞儀をなおした。OSEMもレンジ内。曲率が24mなのでセンタリングに反射光の方向がすごく依存するので、まだアラインメントに確証が持てない。
    * BSも3mradくらいピッチ方向にずれている模様。
 * カメラをインストールしている。マウントとケーブル張りは完了。イルミネーターが課題。(井上)
  * PDの信号がふらついているのでそのチェッックをして欲しい。(和泉)

 * Weekly
  * 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。
 * 問題点など
  * コーチフィルターが不調。
  * PR3の前室のクリーンブースのシートが落ちてしまっているのは直った(中田)。

<<MonthCalendar(KAGRA/Commissioning/DailyWork)>>


----
==== Weekly meeting ====
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||

----
=== Other meetings ===
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])


-----
== Documents ==
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]]

== Communication tools ==

 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

------
Line 6: Line 88:
 * [[KAGRA/Commissioning/ML|Joining commissioning mailing list]]  * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]]

KAGRA Commissioning Wiki


Working people assignment

  • MIF + VIS
    • 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
    • 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
    • 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
    • 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
    • 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
    • 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
    • 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
    • 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
  • * 責任者



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/10/17(Tue)

  • Daily
    • 作業人員(*:責任者)
      • MIF+VIS: *和泉、榎本、中野、神津、新井、正田、井上、灰野、横澤、宮川 (PHS: V-3(榎本), V-7(中野), V-12(横澤))

Fabian、Enzo、平田、

  • Laser hazard
    • PSL直後で100mW、IMC出口で50mW程度、PRM以降は5mW程度。
    • 今日のある時点からハザードエリアがSR2とSR3の間のラインより奥(機械室は除く)になる。
    • 中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。
    • Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを各自1個ずつ持っていって下さい。そして、もし、中央エリアがハザードエリアになった場合は、帰りなどに中央エリアを通る際は保護メガネの着用をお願いします。保護メガネは、前室の入り口横に移動される保護メガネ台に返してください。
    • Xエンドに行く方は保護メガネは必要ありません。
  • 作業
    • アラインメント(中野)
      • BSまで光が到達した。X方向に打ち込んでいる。ゲートバルブのビューポートの端に通っている。
      • PR3のお辞儀をなおした。OSEMもレンジ内。曲率が24mなのでセンタリングに反射光の方向がすごく依存するので、まだアラインメントに確証が持てない。
      • BSも3mradくらいピッチ方向にずれている模様。
  • カメラをインストールしている。マウントとケーブル張りは完了。イルミネーターが課題。(井上)
    • PDの信号がふらついているのでそのチェッックをして欲しい。(和泉)
  • Weekly
    • 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。
  • 問題点など
    • コーチフィルターが不調。
    • PR3の前室のクリーンブースのシートが落ちてしまっているのは直った(中田)。

KAGRA/Commissioning/DailyWork
<< <  2024 / 5 >  >>
Mon Tue Wed Thu Fri Sat Sun
    1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31    


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokum , or educe, Polycom

No.

Date

Agenda

Minute

Files

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1