Line 2: Line 2:
-----
== Working people assignment ==
  
 . * 責任者
 * ビーム位置測定
  * 10/30 *内山、寺田、木村、井上、沢田@IXA
  * 10/31 *内山、寺田、木村、井上、沢田@IXC, IYC
  * 11/1 *内山、寺田、木村、沢田@EXA
  .
  * 11/5 *内山、寺田、木村、井上、沢田@EYA
  * 11/6 *内山、寺田、木村、井上、沢田@IYA
  * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
  .
  * 11/8 *木村、荒木、沢田@IXV, IXC、荒木
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
Line 3: Line 18:
 * [[KAGRA/Commissioning/Meeting|Meeting]]
Line 5: Line 19:
-----
-----
== Meetings ==

----
=== Morning meeting ===

 * Date and time: Every weekday, 9AM
 * Location: Control room, or educe


2017/10/30(Mon)

 * Daily
  * 作業人員(*:責任者)
   * 位置測定: *内山、寺田、木村、井上、沢田@IXA
   * VIS: Mark, Enzo

  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。

  * 作業
   * アラインメント
    * Yエンドでシグナルを見ることができた。PR3でYまでのアラインメントを取り、BSをDC的に戻して、PR3で揺らした。Xエンドより、Yエンドの方が揺れている。BSのダンピングが問題。
   * BSのコイルドライバーをローパワーからハイパワーに変えた。ダンピングの改良が必要。
   * ビーム位置測定
    * IXAのタンクのベローズを外し、ビームを床に落とす。床を見ることができるスクリーンとカメラを設置する。
    * 明日はクライオスタットに入る予定。


 * Weekly
  * 10/30の週: ビーム位置測定。

 * 問題点など
  * コーチフィルターが不調。
  * 防振装置の操作の伝授

<<MonthCalendar(KAGRA/Commissioning/DailyWork)>>


----
==== Weekly meeting ====
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||

----
=== Other meetings ===
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])


-----
== Documents ==
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]]

== Communication tools ==

 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

------
Line 6: Line 91:
 * [[KAGRA/Commissioning/ML|Joining commissioning mailing list]]  * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]]

KAGRA Commissioning Wiki


Working people assignment

  • * 責任者
  • ビーム位置測定
    • 10/30 *内山、寺田、木村、井上、沢田@IXA
    • 10/31 *内山、寺田、木村、井上、沢田@IXC, IYC
    • 11/1 *内山、寺田、木村、沢田@EXA
    • 11/5 *内山、寺田、木村、井上、沢田@EYA
    • 11/6 *内山、寺田、木村、井上、沢田@IYA
    • 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
    • 11/8 *木村、荒木、沢田@IXV, IXC、荒木
    • 11/9 *木村、荒木、沢田@IYV, IYC、荒木



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/10/30(Mon)

  • Daily
    • 作業人員(*:責任者)
      • 位置測定: *内山、寺田、木村、井上、沢田@IXA
      • VIS: Mark, Enzo
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。
      • Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
      • 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。
    • 作業
      • アラインメント
        • Yエンドでシグナルを見ることができた。PR3でYまでのアラインメントを取り、BSをDC的に戻して、PR3で揺らした。Xエンドより、Yエンドの方が揺れている。BSのダンピングが問題。
      • BSのコイルドライバーをローパワーからハイパワーに変えた。ダンピングの改良が必要。
      • ビーム位置測定
        • IXAのタンクのベローズを外し、ビームを床に落とす。床を見ることができるスクリーンとカメラを設置する。
        • 明日はクライオスタットに入る予定。
  • Weekly
    • 10/30の週: ビーム位置測定。
  • 問題点など
    • コーチフィルターが不調。
    • 防振装置の操作の伝授

KAGRA/Commissioning/DailyWork
<< <  2024 / 5 >  >>
Mon Tue Wed Thu Fri Sat Sun
    1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31    


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokum , or educe, Polycom

No.

Date

Agenda

Minute

Files

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings

  • Meeting about PR2 pitch misalignment (Minute)


Documents