Line 2: Line 2:
-----
== Working people assignment ==
  
 . * 責任者
 * ビーム位置測定
  * 10/31 *内山、寺田、木村、井上、沢田@IXC, IYC
  * 11/1 *内山、寺田、木村、沢田@EXA
  .
  * 11/5 *内山、寺田、木村、井上、沢田@EYA
  * 11/6 *内山、寺田、木村、井上、沢田@IYA
  * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
  .
  * 11/8 *木村、荒木、沢田@IXV, IXC、荒木
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
Line 3: Line 17:
 * [[KAGRA/Commissioning/Meeting|Meeting]]
Line 5: Line 18:
-----
-----
== Meetings ==

----
=== Morning meeting ===

 * Date and time: Every weekday, 9AM
 * Location: Control room, or educe


2017/10/30(Mon)

 * Daily
  * 作業人員(*:責任者)
   * 位置測定: *内山、寺田、木村、井上、沢田@IXA, IXC(PHS: V-10寺田、V-9井上)
   * VIS: Mark, Enzo
   * ビーム調整: 中野、三代

  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。

  * 作業
   * アラインメント
   * ビーム位置測定
    * IXAのタンクのベローズを外して、フランジ面を出し、IXA側にスクリーンを置きビームを見た。その位置でビームを床に落とす。ビームがダクト中心に対して53mmだけ-Y側、+13mm上側にずれていた。
    * その時ゲートバルブのビューポートを見たら、IXAからゲートバルブを見て右上側(-Y側)に見えた。
    * EXに光を当てた状態で、PR3の真ん中に入れると、フロントのビューポートの真ん中から3-4cmずれる。PDのカウントが11000程度になり、台風前に戻った。理論値は1.4cmだけ-Y側にずれる。
    * フロントのビューポートの真ん中に入れると、PR3の真ん中からずれる。ただしクリップはされていない。PDのカウントのほとんど改善はなかった。
    * 最後にPR3の真ん中に戻した。
    * 今日は@IXA, IXCでビーム位置を落とす。


 * Weekly
  * 10/30の週: ビーム位置測定。

 * 問題点など
  * コーチフィルターが不調。
  * 防振装置の操作の伝授

<<MonthCalendar(KAGRA/Commissioning/DailyWork)>>


----
==== Weekly meeting ====
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||

----
=== Other meetings ===
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]


-----
== Documents ==
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]]

== Communication tools ==

 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

------
Line 6: Line 95:
 * [[KAGRA/Commissioning/ML|Joining commissioning mailing list]]  * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]]

KAGRA Commissioning Wiki


Working people assignment

  • * 責任者
  • ビーム位置測定
    • 10/31 *内山、寺田、木村、井上、沢田@IXC, IYC
    • 11/1 *内山、寺田、木村、沢田@EXA
    • 11/5 *内山、寺田、木村、井上、沢田@EYA
    • 11/6 *内山、寺田、木村、井上、沢田@IYA
    • 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
    • 11/8 *木村、荒木、沢田@IXV, IXC、荒木
    • 11/9 *木村、荒木、沢田@IYV, IYC、荒木



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/10/30(Mon)

  • Daily
    • 作業人員(*:責任者)
      • 位置測定: *内山、寺田、木村、井上、沢田@IXA, IXC(PHS: V-10寺田、V-9井上)
      • VIS: Mark, Enzo
      • ビーム調整: 中野、三代
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。
      • Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
      • 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。
    • 作業
      • アラインメント
      • ビーム位置測定
        • IXAのタンクのベローズを外して、フランジ面を出し、IXA側にスクリーンを置きビームを見た。その位置でビームを床に落とす。ビームがダクト中心に対して53mmだけ-Y側、+13mm上側にずれていた。
        • その時ゲートバルブのビューポートを見たら、IXAからゲートバルブを見て右上側(-Y側)に見えた。
        • EXに光を当てた状態で、PR3の真ん中に入れると、フロントのビューポートの真ん中から3-4cmずれる。PDのカウントが11000程度になり、台風前に戻った。理論値は1.4cmだけ-Y側にずれる。
        • フロントのビューポートの真ん中に入れると、PR3の真ん中からずれる。ただしクリップはされていない。PDのカウントのほとんど改善はなかった。
        • 最後にPR3の真ん中に戻した。
        • 今日は@IXA, IXCでビーム位置を落とす。
  • Weekly
    • 10/30の週: ビーム位置測定。
  • 問題点など
    • コーチフィルターが不調。
    • 防振装置の操作の伝授

KAGRA/Commissioning/DailyWork
<< <  2024 / 4 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30          


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokum , or educe, Polycom

No.

Date

Agenda

Minute

Files

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1