== Task list ==

=== Phase1 ===
=== Phase2 ===

-----
Line 4: Line 11:
 * MIF + VIS * 責任者
Line 6: Line 13:
  * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
 * ビーム位置測定
  * 11/6 *内山、寺田、木村、井上、沢田@IYA
  * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
Line 12: Line 17:
  * 11/8 *木村、荒木、沢田@IXV, IXC、荒木
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
Line 13: Line 20:
 . * 責任者
Line 15: Line 22:

<<Anchor(Meetings)>>
Line 19: Line 28:
<<Anchor(MorningMeetings)>>
Line 25: Line 35:
2017/10/20(Fri) 2017/11/6(Mon.)
Line 29: Line 39:
   * MIF+VIS: *和泉、榎本、新井、正田、井上、灰野、横澤、土田、Fabian、Enzo、平田 (PHS: V-2(井上), V-3(榎本), V-7(), V-12(横澤))    * 位置測定: *内山、寺田、木村、井上、沢田、灰野、横澤(V-6(井上), V-10(灰野), V-12(横澤))
   * VIS: Mark, Enzo, 神津
Line 32: Line 43:
   * PSL直後で120mW、IMC出口で1000mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。
   * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを使い通過して下さい。メガネはそのまま持って行って、帰りに中央エリアを通る際は再び保護メガネの着用をお願いします。
   * EXA, EYAの真空槽まわりで作業する人は保護メガネをかけください。そばを通るだけの方は保護メガネは必要ありません。
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xエンド1F。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 今日のみXエンド1Fがハザートエリアになりますので、Xエンド1Fで作業をする場合は必ずレーザーグラスをかけてください。
Line 38: Line 49:
   * アラインメント(和泉)
    * 日に日にアラインメントがずれているようだったので、Oplevをキャリブレーションし直した。IMMTなどファクター3とか10間違っていた。
    * Xエンドまで光が通った。直接光かどうかはまだ不明。PDのゲイン調整と、センサーカードで確認予定。
    * PR2が100urad程度揺れている模様。
   * X/Y end
    * EXAにカメラがインストールされた。
    * 200HzのノイズはLEDと判明。リモートでオンオフできないので、現在は消してある。
    * EYAにもビューポーを設置した。EYAにもカメラをつけるかどうか検討する。(井上)
   * ビーム位置測定
    * 日曜 EYAでの位置確認。ビームは縦が10cm、横が10cmを超えるくらい揺れている。GVのセンターの位置を2点落としてきた。
    * 今日はIYAのビーム位置を落とす。
    * XエンドのEXCのビームをTcamで確認できるか試している。今日も引き続き作業を行う。

   * 防振関連
    * 日曜にPR3とBSのアラインメントをOSEMでとったが、その際最初方法がわからず、中野->井上で技術伝承が取られた。
    * BSのexcitationの止め方がわからなかったので、今日確認する。
Line 48: Line 59:
  * 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。->ほぼ目標達成。
  * 10/23の週: Yエンドに光を送る。
  * 11/6の週: 火曜日くらいまでY側のビーム位置測定。
  * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。
Line 58: Line 69:
<<Anchor(WeeklyMeetings)>>
Line 61: Line 73:
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||
[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=
3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
Line 66: Line 80:
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 73: Line 87:
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]

KAGRA Commissioning Wiki


Task list

Phase1

Phase2


Working people assignment

* 責任者

  • ビーム位置測定
    • 11/6 *内山、寺田、木村、井上、沢田@IYA
    • 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
    • 11/8 *木村、荒木、沢田@IXV, IXC、荒木
    • 11/9 *木村、荒木、沢田@IYV, IYC、荒木



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/6(Mon.)

  • Daily
    • 作業人員(*:責任者)
      • 位置測定: *内山、寺田、木村、井上、沢田、灰野、横澤(V-6(井上), V-10(灰野), V-12(横澤))
      • VIS: Mark, Enzo, 神津
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xエンド1F。
      • Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
      • 今日のみXエンド1Fがハザートエリアになりますので、Xエンド1Fで作業をする場合は必ずレーザーグラスをかけてください。
    • 作業
      • ビーム位置測定
        • 日曜 EYAでの位置確認。ビームは縦が10cm、横が10cmを超えるくらい揺れている。GVのセンターの位置を2点落としてきた。
        • 今日はIYAのビーム位置を落とす。
        • XエンドのEXCのビームをTcamで確認できるか試している。今日も引き続き作業を行う。
      • 防振関連
        • 日曜にPR3とBSのアラインメントをOSEMでとったが、その際最初方法がわからず、中野->井上で技術伝承が取られた。

        • BSのexcitationの止め方がわからなかったので、今日確認する。
  • Weekly
    • 11/6の週: 火曜日くらいまでY側のビーム位置測定。
    • フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。
  • 問題点など
    • コーチフィルターが不調。

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokum , or educe, Polycom

No.

Date

Agenda

Schedule

Minute

Files

7

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members